Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
49
matching recommendationsNAICS | 31151 | Dairy Product (except Frozen) Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UK2001 # 11 Y:2020 | 11 | 2020 | OPTIMIZE PLANT POWER FACTOR | $31,564 | $19,285 | Not Implemented |
UK2001 # 10 Y:2020 | 10 | 2020 | REPLACE BOILER | $10,114 | $45,600 | Not Implemented |
UK2001 # 09 Y:2020 | 09 | 2020 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $252,728 | $102,800 | Not Implemented |
UK2001 # 08 Y:2020 | 08 | 2020 | INSULATE BARE EQUIPMENT | $2,547 | $1,006 | Not Implemented |
UK2001 # 07 Y:2020 | 07 | 2020 | CLEAN CONDENSER TUBES | $4,023 | $8,700 | Implemented |
UK2001 # 06 Y:2020 | 06 | 2020 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $118,102 | $6,775 | Not Implemented |
UK2001 # 05 Y:2020 | 05 | 2020 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $8,684 | $2,240 | Not Implemented |
UK2001 # 04 Y:2020 | 04 | 2020 | INSTALL OCCUPANCY SENSORS | $571 | $875 | Implemented |
UK2001 # 03 Y:2020 | 03 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,887 | $9,378 | Implemented |
UK2001 # 02 Y:2020 | 02 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,413 | $0 | Not Implemented |
UK2001 # 01 Y:2020 | 01 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,076 | $2,010 | Implemented |
UK1511 # 02 Y:2015 | 02 | 2015 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $42,293 | $0 | Not Implemented |
UK1511 # 14 Y:2015 | 14 | 2015 | INSULATE FEEDWATER TANK | $1,113 | $862 | Implemented |
UK1511 # 13 Y:2015 | 13 | 2015 | INSTALL TURBULATORS | $8,026 | $9,000 | Not Implemented |
UK1511 # 12 Y:2015 | 12 | 2015 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $7,205 | $18,400 | Not Implemented |
UK1511 # 11 Y:2015 | 11 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $552 | $0 | Implemented |
UK1511 # 10 Y:2015 | 10 | 2015 | USE ONLY CERTIFIED MOTOR REPAIR SHOPS | $2,199 | $1,865 | Not Implemented |
UK1511 # 09 Y:2015 | 09 | 2015 | UPGRADE OBSOLETE EQUIPMENT | $2,127 | $14,000 | Implemented |
UK1511 # 08 Y:2015 | 08 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $737 | $1,500 | Implemented |
UK1511 # 07 Y:2015 | 07 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,050 | $0 | Implemented |
UK1511 # 06 Y:2015 | 06 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,159 | $1,371 | Implemented |
UK1511 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,582 | $51,370 | Implemented |
UK1511 # 04 Y:2015 | 04 | 2015 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $596 | $0 | Implemented |
UK1511 # 03 Y:2015 | 03 | 2015 | OPTIMIZE PLANT POWER FACTOR | $9,011 | $8,260 | Implemented |
UK1511 # 01 Y:2015 | 01 | 2015 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $457,639 | $1,000,000 | Implemented |