Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
563
matching recommendationsNAICS | 311511 | Fluid Milk Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0099 # 02 Y:2005 | 02 | 2005 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $16,520 | $7,062 | Not Implemented |
MI0099 # 03 Y:2005 | 03 | 2005 | UPGRADE CONTROLS ON COMPRESSORS | $11,973 | $2,750 | Implemented |
MI0099 # 04 Y:2005 | 04 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,746 | $4,736 | Not Implemented |
MI0099 # 05 Y:2005 | 05 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,897 | $470 | Implemented |
MI0099 # 06 Y:2005 | 06 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,355 | $1,750 | Implemented |
MI0099 # 07 Y:2005 | 07 | 2005 | USE MINIMUM STEAM OPERATING PRESSURE | $200 | $115 | Implemented |
LL0207 # 01 Y:2004 | 01 | 2004 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $36,769 | $16,000 | Implemented |
LL0207 # 02 Y:2004 | 02 | 2004 | INSULATE BARE EQUIPMENT | $34,833 | $7,488 | Implemented |
LL0207 # 03 Y:2004 | 03 | 2004 | INCREASE AMOUNT OF CONDENSATE RETURNED | $6,837 | $12,236 | Not Implemented |
LL0207 # 04 Y:2004 | 04 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,171 | $225 | Not Implemented |
LL0207 # 05 Y:2004 | 05 | 2004 | REPAIR AND ELIMINATE STEAM LEAKS | $2,149 | $1,960 | Implemented |
LL0207 # 06 Y:2004 | 06 | 2004 | USE PHOTOCELL CONTROLS | $449 | $30 | Not Implemented |
LL0207 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $701 | $525 | Not Implemented |
LL0207 # 08 Y:2004 | 08 | 2004 | INSTALL OCCUPANCY SENSORS | $99 | $120 | Not Implemented |
LL0207 # 09 Y:2004 | 09 | 2004 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $33 | $180 | Not Implemented |
LL0207 # 10 Y:2004 | 10 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $46,500 | $3,150 | Implemented |
LL0207 # 11 Y:2004 | 11 | 2004 | RECOVER AND REUSE COOLING WATER | $11,194 | $32,000 | Not Implemented |
SU0197 # 01 Y:2004 | 01 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $16,106 | $0 | Not Implemented |
SU0197 # 02 Y:2004 | 02 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,301 | $0 | Not Implemented |
SU0197 # 03 Y:2004 | 03 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,966 | $0 | Implemented |
SU0197 # 04 Y:2004 | 04 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,301 | $154 | Implemented |
SU0197 # 05 Y:2004 | 05 | 2004 | INSTALL TURBULATORS | $3,875 | $350 | Not Implemented |
SU0197 # 06 Y:2004 | 06 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,462 | $725 | Implemented |
SU0197 # 07 Y:2004 | 07 | 2004 | USE SYNTHETIC LUBRICANT | $2,982 | $1,000 | Implemented |
SU0197 # 08 Y:2004 | 08 | 2004 | BURN A LESS EXPENSIVE GRADE OF FUEL | $26,570 | $16,638 | Not Implemented |