IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

24

matching recommendations
Reset
NAICS 311511 Fluid Milk Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD1014 # 03 Y:2020 03 2020 USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS $23,635 $0 Not Implemented
UD1014 # 14 Y:2020 14 2020 INSTALL OCCUPANCY SENSORS $594 $1,213 Not Implemented
UD1014 # 13 Y:2020 13 2020 INSTALL OCCUPANCY SENSORS $3,028 $10,386 Not Implemented
UD1014 # 12 Y:2020 12 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,907 $28,900 Not Implemented
UD1014 # 11 Y:2020 11 2020 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $1,972 $5,000 Not Implemented
UD1014 # 10 Y:2020 10 2020 UPGRADE CONTROLS ON COMPRESSORS $2,657 $1,120 Not Implemented
UD1014 # 09 Y:2020 09 2020 UPGRADE CONTROLS ON COMPRESSORS $4,307 $10,000 Not Implemented
UD1014 # 08 Y:2020 08 2020 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS $6,203 $7,500 Not Implemented
UD1014 # 07 Y:2020 07 2020 INSULATE BARE EQUIPMENT $1,509 $2,357 Not Implemented
UD1014 # 06 Y:2020 06 2020 INSULATE BARE EQUIPMENT $4,569 $309 Not Implemented
UD1014 # 05 Y:2020 05 2020 INSULATE BARE EQUIPMENT $28,500 $18,326 Implemented
UD1014 # 04 Y:2020 04 2020 USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS $15,013 $21,000 Not Implemented
UD1014 # 02 Y:2020 02 2020 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS $45,294 $7,500 Not Implemented
UD1014 # 01 Y:2020 01 2020 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,326 $0 Not Implemented
UD0836 # 01 Y:2011 01 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,705 $2,196 Not Implemented
UD0836 # 10 Y:2011 10 2011 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $6,389 $10,000 Not Implemented
UD0836 # 09 Y:2011 09 2011 RECOVER WASTE HEAT FROM EQUIPMENT $25,293 $18,000 Not Implemented
UD0836 # 08 Y:2011 08 2011 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $30,572 $99,100 Not Implemented
UD0836 # 07 Y:2011 07 2011 USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS $12,875 $15,000 Not Implemented
UD0836 # 06 Y:2011 06 2011 INSTALL / REPAIR INSULATION ON STEAM LINES $1,960 $1,140 Not Implemented
UD0836 # 05 Y:2011 05 2011 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $14,178 $1,000 Not Implemented
UD0836 # 04 Y:2011 04 2011 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $37,847 $32,000 Not Implemented
UD0836 # 03 Y:2011 03 2011 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,689 $7,000 Not Implemented
UD0836 # 02 Y:2011 02 2011 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,796 $36 Not Implemented