IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

107

matching recommendations
Reset
NAICS 3116 Animal Slaughtering and Processing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0670 # 02 Y:2003 02 2003 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,120 $0 Implemented
OK0670 # 07 Y:2003 07 2003 INSTALL AUTOMATIC PACKING EQUIPMENT $58,240 $6,500 Not Implemented
OK0670 # 05 Y:2003 05 2003 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $43,797 $113,450 Not Implemented
OK0670 # 03 Y:2003 03 2003 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE $12,292 $0 Implemented
OK0670 # 01 Y:2003 01 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $20,939 $27,543 Not Implemented
OK0670 # 06 Y:2003 06 2003 INSTALL OCCUPANCY SENSORS $1,771 $1,017 Not Implemented
OK0670 # 04 Y:2003 04 2003 RECOVER WASTE HEAT FROM EQUIPMENT $26,304 $4,211 Not Implemented
SF0268 # 06 Y:2003 06 2003 INSTALL SKYLIGHTS $2,077 $1,440 Not Implemented
SF0268 # 05 Y:2003 05 2003 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,955 $2,574 Not Implemented
SF0268 # 04 Y:2003 04 2003 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,663 $1,080 Not Implemented
SF0268 # 03 Y:2003 03 2003 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $19,165 $10,225 Not Implemented
SF0268 # 02 Y:2003 02 2003 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $425 $175 Not Implemented
SF0268 # 01 Y:2003 01 2003 IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS $486 $0 Not Implemented
SF0268 # 07 Y:2003 07 2003 INSULATE FEEDWATER TANK $527 $1,186 Not Implemented
SF0268 # 08 Y:2003 08 2003 REUSE / RECYCLE/ SELL PAPER PRODUCTS $3,280 $800 Not Implemented
WV0277 # 05 Y:2003 05 2003 INSULATE BARE EQUIPMENT $61,699 $29,824 Implemented
WV0277 # 02 Y:2003 02 2003 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $10,711 $1,000 Implemented
WV0277 # 01 Y:2003 01 2003 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $110,201 $2,195 Not Implemented
WV0277 # 04 Y:2003 04 2003 RECOVER AND REUSE WASTE MATERIAL $65,102 $250,000 Not Implemented
WV0277 # 03 Y:2003 03 2003 MINIMIZE WATER USAGE $56,297 $17,800 Not Implemented
WV0277 # 06 Y:2003 06 2003 REPAIR AND ELIMINATE STEAM LEAKS $40,926 $450 Implemented
WV0277 # 10 Y:2003 10 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,044 $0 Not Implemented
WV0277 # 12 Y:2003 12 2003 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $931 $470 Not Implemented
WV0277 # 08 Y:2003 08 2003 OPTIMIZE PLANT POWER FACTOR $10,739 $62,060 Implemented
WV0277 # 09 Y:2003 09 2003 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $6,204 $5,175 Implemented