Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 2003 |
Principal Product | Beef jerky |
NAICS | 311612 - Meat Processed from Carcasses |
SIC | 2013 - Sausages And Other Prepared Meats |
Sales | $50,000,000-$100,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 45,000 |
Annual Production | 75,000,000 Pounds |
Production Hrs. Annual | 8,400 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $292,692 | 2,742,800 | kWh | $0.11 |
Electricity Demand | $61,186 | 5,524 | kW-months/year | $11.08 |
Natural Gas | $146,619 | 23,656 | MMBtu | $6.20 |
TOTAL ENERGY COSTS | $585,997 | |||
RECOMMENDED SAVINGS* | $31,578 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.7312 IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS |
Savings: $486 Cost: - |
$486 | 7,357 | - | - | - | - | - | - |
$486 7,357 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7132 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS |
Savings: $425 Cost: $175 |
$359 | 3,360 | $66 | 6 | - | - | - | - |
$359 3,360 kWh |
$66 6 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE |
Savings: $19,165 Cost: $10,225 |
$17,957 | 168,120 | $1,208 | 109 | - | - | - | - |
$17,957 168,120 kWh |
$1,208 109 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,663 Cost: $1,080 |
$1,436 | 14,380 | $227 | 21 | - | - | - | - |
$1,436 14,380 kWh |
$227 21 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,955 Cost: $2,574 |
$3,445 | 32,256 | $510 | 46 | - | - | - | - |
$3,445 32,256 kWh |
$510 46 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7145 INSTALL SKYLIGHTS |
Savings: $2,077 Cost: $1,440 |
$1,800 | 16,850 | $277 | 25 | - | - | - | - |
$1,800 16,850 kWh |
$277 25 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2123 INSULATE FEEDWATER TANK |
Savings: $527 Cost: $1,186 |
- | - | - | - | $527 | 85 | - | - |
- - kWh |
- - kW-months/year |
$527 85 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5217 REUSE / RECYCLE/ SELL PAPER PRODUCTS |
Savings: $3,280 Cost: $800 |
- | - | - | - | - | - | $3,280 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$3,280 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $31,578 Cost: $17,480 |
$25,483 | 242,323 | $2,288 | 207 | $527 | 85 | $3,280 | - | $25,483 242,323 kWh |
$2,288 207 kW-months/year |
$527 85 MMBtu |
$3,280 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |