Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
491
matching recommendationsNAICS | 311612 | Meat Processed from Carcasses |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0785 # 07 Y:2008 | 07 | 2008 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $4,742 | $5,924 | Implemented |
UD0785 # 08 Y:2008 | 08 | 2008 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,606 | $0 | Not Implemented |
UD0785 # 09 Y:2008 | 09 | 2008 | OPTIMIZE PLANT POWER FACTOR | $3,317 | $4,500 | Not Implemented |
UD0785 # 10 Y:2008 | 10 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,512 | $1,000 | Implemented |
UD0785 # 11 Y:2008 | 11 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,180 | $0 | Not Implemented |
IA0424 # 01 Y:2008 | 01 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $333 | $13 | Implemented |
IA0424 # 02 Y:2008 | 02 | 2008 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,811 | $134 | Not Implemented |
IA0424 # 03 Y:2008 | 03 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,627 | $3,004 | Implemented |
IA0424 # 04 Y:2008 | 04 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,324 | $4,198 | Not Implemented |
IA0424 # 05 Y:2008 | 05 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,992 | $7,650 | Implemented |
IA0424 # 06 Y:2008 | 06 | 2008 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $801 | $780 | Implemented |
SU0262 # 01 Y:2008 | 01 | 2008 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $5,029 | $0 | Implemented |
SU0262 # 02 Y:2008 | 02 | 2008 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $4,309 | $0 | Not Implemented |
SU0262 # 03 Y:2008 | 03 | 2008 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $1,352 | $0 | Not Implemented |
SU0262 # 04 Y:2008 | 04 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,275 | $392 | Not Implemented |
SU0262 # 05 Y:2008 | 05 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,882 | $5,215 | Implemented |
SU0262 # 06 Y:2008 | 06 | 2008 | INSTALL / REPAIR INSULATION ON STEAM LINES | $338 | $577 | Not Implemented |
SU0262 # 07 Y:2008 | 07 | 2008 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $183 | $308 | Not Implemented |
SU0262 # 08 Y:2008 | 08 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,400 | $10,328 | Implemented |
SU0262 # 09 Y:2008 | 09 | 2008 | INSTALL OCCUPANCY SENSORS | $320 | $716 | Not Implemented |
LL0284 # 01 Y:2007 | 01 | 2007 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $52,170 | $49,000 | Not Implemented |
LL0284 # 02 Y:2007 | 02 | 2007 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $33,682 | $1,600 | Not Implemented |
LL0284 # 03 Y:2007 | 03 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $21,045 | $12,575 | Not Implemented |
LL0284 # 04 Y:2007 | 04 | 2007 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $16,900 | $1,500 | Not Implemented |
LL0284 # 05 Y:2007 | 05 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,314 | $2,100 | Not Implemented |