Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
61
matching recommendationsNAICS | 3119 | Other Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0870 # 04 Y:2013 | 04 | 2013 | MAKE ICE DURING OFF PEAK HOURS FOR COOLING | $20,022 | $105,120 | Not Implemented |
OK0870 # 01 Y:2013 | 01 | 2013 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $8,384 | $0 | Implemented |
OK0870 # 03 Y:2013 | 03 | 2013 | DEVELOP A REPAIR/REPLACE POLICY | $1,212 | $2,500 | Not Implemented |
OK0870 # 02 Y:2013 | 02 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,957 | $0 | Implemented |
BS0020 # 06 Y:2013 | 06 | 2013 | COVER OPEN TANKS | $3,845 | $6,050 | Not Implemented |
BS0020 # 04 Y:2013 | 04 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,831 | $15,600 | Implemented |
BS0020 # 05 Y:2013 | 05 | 2013 | INSULATE BARE EQUIPMENT | $9,887 | $5,300 | Implemented |
BS0020 # 03 Y:2013 | 03 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,893 | $71,307 | Implemented |
BS0020 # 02 Y:2013 | 02 | 2013 | OPTIMIZE PLANT POWER FACTOR | $18,318 | $19,262 | Implemented |
BS0020 # 01 Y:2013 | 01 | 2013 | REDESIGN PROCESS | $15,024 | $15,359 | Not Implemented |
TT0114 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $360 | $315 | Implemented |
TT0114 # 07 Y:2013 | 07 | 2013 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $7,988 | $15,000 | Not Implemented |
TT0114 # 06 Y:2013 | 06 | 2013 | INSTALL OCCUPANCY SENSORS | $6,033 | $5,950 | Implemented |
TT0114 # 04 Y:2013 | 04 | 2013 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $6,310 | $9,125 | Not Implemented |
TT0114 # 03 Y:2013 | 03 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $13,529 | $125 | Implemented |
TT0114 # 01 Y:2013 | 01 | 2013 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $7,820 | $0 | Implemented |
TT0114 # 02 Y:2013 | 02 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $42 | $0 | Implemented |
MA0712 # 03 Y:2013 | 03 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,311 | $5,000 | Implemented |
MA0712 # 02 Y:2013 | 02 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,863 | $12,000 | Implemented |
MA0712 # 05 Y:2013 | 05 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $938 | $2,930 | Not Implemented |
MA0712 # 06 Y:2013 | 06 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $853 | $2,930 | Not Implemented |
MA0712 # 04 Y:2013 | 04 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,440 | $4,200 | Not Implemented |
MA0712 # 07 Y:2013 | 07 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $827 | $1,200 | Implemented |
MA0712 # 01 Y:2013 | 01 | 2013 | USE RADIANT HEATER FOR SPOT HEATING | $13,420 | $65,327 | Implemented |
MA0712 # 08 Y:2013 | 08 | 2013 | INSULATE BARE EQUIPMENT | $323 | $750 | Implemented |