Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
298
matching recommendationsNAICS | 31199 | All Other Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0870 # 01 Y:2013 | 01 | 2013 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $8,384 | $0 | Implemented |
OK0870 # 04 Y:2013 | 04 | 2013 | MAKE ICE DURING OFF PEAK HOURS FOR COOLING | $20,022 | $105,120 | Not Implemented |
OK0870 # 02 Y:2013 | 02 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,957 | $0 | Implemented |
OK0870 # 03 Y:2013 | 03 | 2013 | DEVELOP A REPAIR/REPLACE POLICY | $1,212 | $2,500 | Not Implemented |
BS0020 # 01 Y:2013 | 01 | 2013 | REDESIGN PROCESS | $15,024 | $15,359 | Not Implemented |
BS0020 # 02 Y:2013 | 02 | 2013 | OPTIMIZE PLANT POWER FACTOR | $18,318 | $19,262 | Implemented |
BS0020 # 05 Y:2013 | 05 | 2013 | INSULATE BARE EQUIPMENT | $9,887 | $5,300 | Implemented |
BS0020 # 03 Y:2013 | 03 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,893 | $71,307 | Implemented |
BS0020 # 04 Y:2013 | 04 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,831 | $15,600 | Implemented |
BS0020 # 06 Y:2013 | 06 | 2013 | COVER OPEN TANKS | $3,845 | $6,050 | Not Implemented |
TT0114 # 07 Y:2013 | 07 | 2013 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $7,988 | $15,000 | Not Implemented |
TT0114 # 01 Y:2013 | 01 | 2013 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $7,820 | $0 | Implemented |
TT0114 # 06 Y:2013 | 06 | 2013 | INSTALL OCCUPANCY SENSORS | $6,033 | $5,950 | Implemented |
TT0114 # 02 Y:2013 | 02 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $42 | $0 | Implemented |
TT0114 # 04 Y:2013 | 04 | 2013 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $6,310 | $9,125 | Not Implemented |
TT0114 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $360 | $315 | Implemented |
TT0114 # 03 Y:2013 | 03 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $13,529 | $125 | Implemented |
BS0010 # 03 Y:2012 | 03 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,826 | $750 | Not Implemented |
BS0010 # 05 Y:2012 | 05 | 2012 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $70 | $60 | Not Implemented |
BS0010 # 02 Y:2012 | 02 | 2012 | INSULATE BARE EQUIPMENT | $222 | $512 | Implemented |
BS0010 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $645 | $251 | Implemented |
BS0010 # 01 Y:2012 | 01 | 2012 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $289 | $630 | Not Implemented |
LE0348 # 02 Y:2012 | 02 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,828 | $5,000 | Not Implemented |
LE0348 # 03 Y:2012 | 03 | 2012 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $12,235 | $43,550 | Not Implemented |
LE0348 # 04 Y:2012 | 04 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,951 | $1,940 | Not Implemented |