Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
500
matching recommendationsNAICS | 311999 | All Other Miscellaneous Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0114 # 07 Y:2013 | 07 | 2013 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $7,988 | $15,000 | Not Implemented |
BS0010 # 01 Y:2012 | 01 | 2012 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $289 | $630 | Not Implemented |
BS0010 # 02 Y:2012 | 02 | 2012 | INSULATE BARE EQUIPMENT | $222 | $512 | Implemented |
BS0010 # 03 Y:2012 | 03 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,826 | $750 | Not Implemented |
BS0010 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $645 | $251 | Implemented |
BS0010 # 05 Y:2012 | 05 | 2012 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $70 | $60 | Not Implemented |
BS0008 # 01 Y:2012 | 01 | 2012 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $9,360 | $350 | Not Implemented |
BS0008 # 02 Y:2012 | 02 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,298 | $14,400 | Not Implemented |
BS0008 # 03 Y:2012 | 03 | 2012 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,079 | $117 | Not Implemented |
BS0008 # 04 Y:2012 | 04 | 2012 | USE PHOTOCELL CONTROLS | $427 | $227 | Not Implemented |
BS0008 # 05 Y:2012 | 05 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $475 | $15 | Not Implemented |
BD0397 # 01 Y:2011 | 01 | 2011 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $23,085 | $6,000 | Not Implemented |
BD0397 # 02 Y:2011 | 02 | 2011 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $15,024 | $14,500 | Not Implemented |
BD0397 # 03 Y:2011 | 03 | 2011 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $7,550 | $6,000 | Not Implemented |
BD0397 # 04 Y:2011 | 04 | 2011 | INSTALL OCCUPANCY SENSORS | $6,237 | $4,440 | Not Implemented |
BD0397 # 05 Y:2011 | 05 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,796 | $765 | Not Implemented |
BD0397 # 06 Y:2011 | 06 | 2011 | INSTALL TURBULATORS | $4,508 | $1,500 | Not Implemented |
BD0397 # 07 Y:2011 | 07 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,439 | $650 | Not Implemented |
BD0397 # 08 Y:2011 | 08 | 2011 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,214 | $5,820 | Not Implemented |
DL0066 # 01 Y:2011 | 01 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,960 | $1,035 | Implemented |
DL0066 # 02 Y:2011 | 02 | 2011 | USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR | $101,455 | $36,300 | Not Implemented |
DL0066 # 03 Y:2011 | 03 | 2011 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $2,460 | $2,000 | Implemented |
DL0066 # 04 Y:2011 | 04 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,015 | $4,000 | Implemented |
DL0066 # 05 Y:2011 | 05 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,701 | $1,257 | Not Implemented |
DL0066 # 06 Y:2011 | 06 | 2011 | UPGRADE CONTROLS ON COMPRESSORS | $12,600 | $10,000 | Not Implemented |