Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
42
matching recommendationsNAICS | 311999 | All Other Miscellaneous Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KS2324 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,738 | $5,480 | n/a |
KS2324 # 03 Y:2023 | 03 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $32,201 | $0 | n/a |
KS2324 # 04 Y:2023 | 04 | 2023 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $12,787 | $8,320 | n/a |
KS2324 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,344 | $22,467 | n/a |
KS2324 # 06 Y:2023 | 06 | 2023 | INSTALL OCCUPANCY SENSORS | $2,028 | $4,064 | n/a |
KS2324 # 07 Y:2023 | 07 | 2023 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $57,559 | $312,824 | n/a |
KS2324 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $63,860 | $598,739 | n/a |
OR0782 # 02 Y:2023 | 02 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $34,701 | $316,866 | n/a |
OR0782 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,455 | $3,143 | n/a |
OR0782 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $4,302 | $41,745 | n/a |
LE0554 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,979 | $40,491 | Implemented |
LE0554 # 05 Y:2023 | 05 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,367 | $4,000 | Implemented |
LE0554 # 06 Y:2023 | 06 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $873 | $2,700 | Implemented |
LE0554 # 07 Y:2023 | 07 | 2023 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $31,394 | $144,000 | Not Implemented |
LE0554 # 08 Y:2023 | 08 | 2023 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $10,658 | $49,017 | Not Implemented |
LE0554 # 09 Y:2023 | 09 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $193,840 | $880,000 | Not Implemented |
LE0554 # 10 Y:2023 | 10 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $18,296 | $86,535 | Implemented |
LE0554 # 11 Y:2023 | 11 | 2023 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $44,665 | $369,354 | Not Implemented |
LE0554 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,873 | $35,440 | Implemented |
LE0554 # 02 Y:2023 | 02 | 2023 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $2,747 | $5,000 | Implemented |
LE0554 # 01 Y:2023 | 01 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $30,649 | $26,194 | Implemented |
UL2303 # 04 Y:2023 | 04 | 2023 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,140 | $7,650 | Not Implemented |
UL2303 # 03 Y:2023 | 03 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,439 | $34,126 | Not Implemented |
UL2303 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,504 | $0 | Not Implemented |
UL2303 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $43,641 | $26,163 | Not Implemented |