Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
984
matching recommendationsNAICS | 31211 | Soft Drink and Ice Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS1904 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $64,763 | $45,810 | Implemented |
LS1904 # 07 Y:2019 | 07 | 2019 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $24,052 | $20,000 | Not Implemented |
OK0997 # 01 Y:2019 | 01 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $29,994 | $49,087 | Not Implemented |
OK0997 # 02 Y:2019 | 02 | 2019 | INSTALL TIMERS AND/OR THERMOSTATS | $17,569 | $1,795 | Implemented |
OK0997 # 03 Y:2019 | 03 | 2019 | OPTIMIZE PLANT POWER FACTOR | $6,052 | $14,332 | Not Implemented |
OK0997 # 04 Y:2019 | 04 | 2019 | RECOVER WASTE HEAT FROM EQUIPMENT | $7,415 | $2,668 | Implemented |
OK0997 # 05 Y:2019 | 05 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,238 | $0 | Implemented |
OK0997 # 06 Y:2019 | 06 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,715 | $1,306 | Implemented |
OK0997 # 07 Y:2019 | 07 | 2019 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $4,032 | $0 | Implemented |
OK0997 # 08 Y:2019 | 08 | 2019 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,875 | $0 | Implemented |
OK0997 # 09 Y:2019 | 09 | 2019 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $663 | $2,640 | Not Implemented |
OK0997 # 10 Y:2019 | 10 | 2019 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $366 | $485 | Implemented |
LS1812 # 01 Y:2018 | 01 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,387 | $50 | Not Implemented |
LS1812 # 02 Y:2018 | 02 | 2018 | RECOVER WASTE HEAT FROM EQUIPMENT | $17,980 | $20,000 | Not Implemented |
LS1812 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22,886 | $17,000 | Implemented |
LS1812 # 04 Y:2018 | 04 | 2018 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,243 | $13,500 | Not Implemented |
AM0757 # 01 Y:2018 | 01 | 2018 | TURN OFF EQUIPMENT WHEN NOT IN USE | $65,410 | $255 | Implemented |
AM0757 # 02 Y:2018 | 02 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $12,154 | $1,140 | Implemented |
AM0757 # 03 Y:2018 | 03 | 2018 | OPTIMIZE PLANT POWER FACTOR | $25,420 | $82,110 | Not Implemented |
AM0757 # 04 Y:2018 | 04 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,856 | $3,000 | Implemented |
AM0757 # 05 Y:2018 | 05 | 2018 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $47,160 | $136 | Implemented |
AM0757 # 06 Y:2018 | 06 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,069 | $28,981 | Implemented |
AM0757 # 07 Y:2018 | 07 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,340 | $17 | Implemented |
UA0197 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,401 | $5,562 | Implemented |
UA0197 # 02 Y:2018 | 02 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,943 | $2,465 | Implemented |