Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
61
matching recommendationsNAICS | 31211 | Soft Drink and Ice Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0406 # 06 Y:2007 | 06 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,557 | $714 | Implemented |
UF0406 # 04 Y:2007 | 04 | 2007 | CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS | $6,004 | $399 | Not Implemented |
UF0406 # 02 Y:2007 | 02 | 2007 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $372 | $289 | Not Implemented |
UF0406 # 03 Y:2007 | 03 | 2007 | INSTALL SET-BACK TIMERS | $6,690 | $625 | Not Implemented |
UF0406 # 05 Y:2007 | 05 | 2007 | REPAIR AND ELIMINATE STEAM LEAKS | $17,857 | $619 | Implemented |
UF0406 # 10 Y:2007 | 10 | 2007 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $18,733 | $6,479 | Not Implemented |
UF0406 # 09 Y:2007 | 09 | 2007 | USE OPTIMUM THICKNESS INSULATION | $7,084 | $1,380 | Implemented |
UF0406 # 01 Y:2007 | 01 | 2007 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $1,441 | $253 | Not Implemented |
UF0406 # 07 Y:2007 | 07 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $229,959 | $0 | Implemented |
UF0406 # 11 Y:2007 | 11 | 2007 | INSTALL AN UNINTERUPTABLE POWER SUPPLY | $4,744,561 | $5,831 | Not Implemented |
UF0406 # 08 Y:2007 | 08 | 2007 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $6,754 | $22,000 | Not Implemented |
DL0008 # 02 Y:2007 | 02 | 2007 | REPLACE BOILER | $33,159 | $102,000 | Not Implemented |
DL0008 # 10 Y:2007 | 10 | 2007 | INSTALL OCCUPANCY SENSORS | $754 | $285 | Implemented |
DL0008 # 09 Y:2007 | 09 | 2007 | USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS | $2,893 | $14,000 | Not Implemented |
DL0008 # 08 Y:2007 | 08 | 2007 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $3,800 | $900 | Implemented |
DL0008 # 07 Y:2007 | 07 | 2007 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,978 | $2,105 | Implemented |
DL0008 # 06 Y:2007 | 06 | 2007 | REPLACE BOILER | $12,509 | $27,400 | Not Implemented |
DL0008 # 05 Y:2007 | 05 | 2007 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $18,000 | $1,000 | Implemented |
DL0008 # 04 Y:2007 | 04 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,801 | $175,000 | Implemented |
DL0008 # 03 Y:2007 | 03 | 2007 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $31,900 | $0 | Implemented |
DL0008 # 01 Y:2007 | 01 | 2007 | RECOVER WASTE HEAT FROM EQUIPMENT | $40,014 | $14,000 | Implemented |
IA0414 # 01 Y:2007 | 01 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,590 | $3,793 | Not Implemented |
IA0414 # 02 Y:2007 | 02 | 2007 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $501 | $118 | Not Implemented |
IA0414 # 03 Y:2007 | 03 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $807 | $262 | Not Implemented |
IA0414 # 04 Y:2007 | 04 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,004 | $163 | Not Implemented |