Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
61
matching recommendationsNAICS | 312111 | Soft Drink Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0575 # 10 Y:2024 | 10 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $25,217 | $144,000 | n/a |
LE0575 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $23,173 | $100 | n/a |
LE0575 # 02 Y:2024 | 02 | 2024 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $6,164 | $100 | n/a |
LE0575 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $45,906 | $7,700 | n/a |
LE0575 # 04 Y:2024 | 04 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $118,088 | $80,000 | n/a |
LE0575 # 05 Y:2024 | 05 | 2024 | INSULATE BARE EQUIPMENT | $37,603 | $28,720 | n/a |
LE0575 # 06 Y:2024 | 06 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $242,187 | $285,000 | n/a |
LE0575 # 07 Y:2024 | 07 | 2024 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $83,526 | $121,547 | n/a |
LE0575 # 08 Y:2024 | 08 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $1,618 | $2,720 | n/a |
LE0575 # 09 Y:2024 | 09 | 2024 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $36,513 | $150,000 | n/a |
DL0188 # 13 Y:2021 | 13 | 2021 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,000 | $5,500 | Not Implemented |
DL0188 # 01 Y:2021 | 01 | 2021 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $900 | $0 | Implemented |
DL0188 # 02 Y:2021 | 02 | 2021 | METER WASTE WATER | $172,100 | $3,000 | Not Implemented |
DL0188 # 04 Y:2021 | 04 | 2021 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $860 | $81,000 | Implemented |
DL0188 # 05 Y:2021 | 05 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $8,798 | $1,000 | Implemented |
DL0188 # 06 Y:2021 | 06 | 2021 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,987 | $20,000 | Not Implemented |
DL0188 # 07 Y:2021 | 07 | 2021 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $1,320 | $8,000 | Not Implemented |
DL0188 # 08 Y:2021 | 08 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $19,340 | $48,750 | Not Implemented |
DL0188 # 09 Y:2021 | 09 | 2021 | RECOVER WASTE HEAT FROM EQUIPMENT | $7,620 | $7,000 | Not Implemented |
DL0188 # 10 Y:2021 | 10 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,490 | $25,000 | Implemented |
DL0188 # 11 Y:2021 | 11 | 2021 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,150 | $4,600 | Not Implemented |
DL0188 # 12 Y:2021 | 12 | 2021 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $25,290 | $57,350 | Implemented |
DL0188 # 03 Y:2021 | 03 | 2021 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $23,050 | $9,490 | Implemented |
DL0188 # 14 Y:2021 | 14 | 2021 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $11,800 | $9,120 | Not Implemented |
LE0452 # 02 Y:2018 | 02 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,260 | $600 | Not Implemented |