matching recommendationsNAICS | 313310 | Textile and Fabric Finishing Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0653 # 06 Y:2009 | 06 | 2009 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,375 | $6,125 | Not Implemented |
MA0653 # 05 Y:2009 | 05 | 2009 | INSULATE BARE EQUIPMENT | $2,840 | $7,510 | Implemented |
MA0653 # 04 Y:2009 | 04 | 2009 | CLOSE OFF UNNEEDED STEAM LINES | $3,551 | $500 | Not Implemented |
MA0653 # 03 Y:2009 | 03 | 2009 | REDUCE VENTILATION AIR | $16,188 | $752 | Implemented |
MA0653 # 02 Y:2009 | 02 | 2009 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $37,210 | $68,000 | Not Implemented |
MA0653 # 01 Y:2009 | 01 | 2009 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $110,550 | $270,000 | Not Implemented |
LE0291 # 09 Y:2009 | 09 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $26,236 | $81,400 | Not Implemented |
LE0291 # 11 Y:2009 | 11 | 2009 | INSTALL OCCUPANCY SENSORS | $3,572 | $1,050 | Not Implemented |
LE0291 # 10 Y:2009 | 10 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,803 | $19,856 | Not Implemented |
LE0291 # 01 Y:2009 | 01 | 2009 | REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT | $32,078 | $50,000 | Not Implemented |
LE0291 # 08 Y:2009 | 08 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,836 | $560 | Implemented |
LE0291 # 07 Y:2009 | 07 | 2009 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,975 | $3,460 | Not Implemented |
LE0291 # 06 Y:2009 | 06 | 2009 | INSTALL TIMERS AND/OR THERMOSTATS | $2,837 | $125 | Not Implemented |
LE0291 # 05 Y:2009 | 05 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,439 | $1,600 | Not Implemented |
LE0291 # 04 Y:2009 | 04 | 2009 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $6,457 | $1,120 | Implemented |
LE0291 # 03 Y:2009 | 03 | 2009 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $15,557 | $2,500 | Implemented |
LE0291 # 02 Y:2009 | 02 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $22,489 | $510 | Not Implemented |