Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
22
matching recommendationsNAICS | 314999 | All Other Miscellaneous Textile Product Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KS2203 # 08 Y:2022 | 08 | 2022 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $10,802 | $59,793 | Not Implemented |
KS2203 # 07 Y:2022 | 07 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,941 | $13,595 | Implemented |
KS2203 # 06 Y:2022 | 06 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,676 | $45 | Implemented |
KS2203 # 05 Y:2022 | 05 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,656 | $5,480 | Implemented |
KS2203 # 04 Y:2022 | 04 | 2022 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $98,216 | $570,000 | Implemented |
KS2203 # 03 Y:2022 | 03 | 2022 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $27,117 | $60,601 | Not Implemented |
KS2203 # 02 Y:2022 | 02 | 2022 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,131 | $0 | Implemented |
KS2203 # 01 Y:2022 | 01 | 2022 | INSTALL / REPAIR INSULATION ON STEAM LINES | $6,958 | $5,101 | Implemented |
GT0817 # 06 Y:2006 | 06 | 2006 | UPGRADE CONTROLS ON COMPRESSORS | $2,666 | $1,500 | Implemented |
GT0817 # 08 Y:2006 | 08 | 2006 | COMBINE UTILITY METERS | $1,987 | $0 | Not Implemented |
GT0817 # 07 Y:2006 | 07 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $32,042 | $15,000 | Not Implemented |
GT0817 # 05 Y:2006 | 05 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,652 | $500 | Implemented |
GT0817 # 04 Y:2006 | 04 | 2006 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $3,469 | $7,920 | Not Implemented |
GT0817 # 03 Y:2006 | 03 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,177 | $9,625 | Not Implemented |
GT0817 # 02 Y:2006 | 02 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $40,933 | $164,201 | Not Implemented |
GT0817 # 01 Y:2006 | 01 | 2006 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $8,981 | $1,333 | Implemented |
GT0804 # 01 Y:2005 | 01 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,261 | $1,200 | Not Implemented |
GT0804 # 06 Y:2005 | 06 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,303 | $1,600 | Implemented |
GT0804 # 05 Y:2005 | 05 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,432 | $2,500 | Implemented |
GT0804 # 04 Y:2005 | 04 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $49,306 | $75,000 | Not Implemented |
GT0804 # 03 Y:2005 | 03 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $15,926 | $12,224 | Implemented |
GT0804 # 02 Y:2005 | 02 | 2005 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $289 | $500 | Implemented |