Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
44
matching recommendationsNAICS | 321 | Wood Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0983 # 02 Y:2024 | 02 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $566 | $1,625 | n/a |
GT0983 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $51,238 | $1,850 | n/a |
GT0983 # 03 Y:2024 | 03 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $101,821 | $1,492,532 | n/a |
KS2427 # 06 Y:2024 | 06 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $45,498 | $453,376 | n/a |
KS2427 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $50,928 | $156,644 | n/a |
KS2427 # 04 Y:2024 | 04 | 2024 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $69,076 | $156,917 | n/a |
KS2427 # 03 Y:2024 | 03 | 2024 | USE OPTIMUM THICKNESS INSULATION | $9,550 | $6,688 | n/a |
KS2427 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,324 | $5,480 | n/a |
KS2427 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,216 | $90 | n/a |
GT0955 # 03 Y:2021 | 03 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,967 | $1,850 | Implemented |
GT0955 # 05 Y:2021 | 05 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,445 | $4,419 | Implemented |
GT0955 # 06 Y:2021 | 06 | 2021 | USE SOLAR HEAT TO MAKE ELECTRICTY | $70,408 | $429,498 | Not Implemented |
GT0955 # 02 Y:2021 | 02 | 2021 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $5,146 | $2,000 | Implemented |
GT0955 # 04 Y:2021 | 04 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $295 | $477 | Not Implemented |
GT0955 # 01 Y:2021 | 01 | 2021 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $7,515 | $2,000 | Not Implemented |
GT0765 # 09 Y:2003 | 09 | 2003 | REPAIR AND ELIMINATE STEAM LEAKS | $1,155 | $300 | Not Implemented |
GT0765 # 10 Y:2003 | 10 | 2003 | BURN A LESS EXPENSIVE GRADE OF FUEL | $61,630 | $250,000 | Not Implemented |
GT0765 # 11 Y:2003 | 11 | 2003 | REPLACE ELECTRIC MOTOR WITH FOSSIL FUEL ENGINE | $7,430 | $12,000 | Not Implemented |
GT0765 # 01 Y:2003 | 01 | 2003 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $3,130 | $0 | Implemented |
GT0765 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,790 | $1,300 | Implemented |
GT0765 # 03 Y:2003 | 03 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $940 | $1,106 | Not Implemented |
GT0765 # 04 Y:2003 | 04 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,180 | $6,000 | Implemented |
GT0765 # 05 Y:2003 | 05 | 2003 | USE MINIMUM STEAM OPERATING PRESSURE | $750 | $0 | Not Implemented |
GT0765 # 06 Y:2003 | 06 | 2003 | IMPROVE LUBRICATION PRACTICES | $320 | $0 | Not Implemented |
GT0765 # 07 Y:2003 | 07 | 2003 | TREAT AND REUSE RINSE WATERS | $1,775 | $5,450 | Not Implemented |