Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
25
matching recommendationsNAICS | 321211 | Hardwood Veneer and Plywood Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0765 # 11 Y:2003 | 11 | 2003 | REPLACE ELECTRIC MOTOR WITH FOSSIL FUEL ENGINE | $7,430 | $12,000 | Not Implemented |
GT0765 # 10 Y:2003 | 10 | 2003 | BURN A LESS EXPENSIVE GRADE OF FUEL | $61,630 | $250,000 | Not Implemented |
GT0765 # 09 Y:2003 | 09 | 2003 | REPAIR AND ELIMINATE STEAM LEAKS | $1,155 | $300 | Not Implemented |
GT0765 # 08 Y:2003 | 08 | 2003 | INSTALL / REPAIR INSULATION ON STEAM LINES | $420 | $460 | Not Implemented |
GT0765 # 07 Y:2003 | 07 | 2003 | TREAT AND REUSE RINSE WATERS | $1,775 | $5,450 | Not Implemented |
GT0765 # 06 Y:2003 | 06 | 2003 | IMPROVE LUBRICATION PRACTICES | $320 | $0 | Not Implemented |
GT0765 # 01 Y:2003 | 01 | 2003 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $3,130 | $0 | Implemented |
GT0765 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,790 | $1,300 | Implemented |
GT0765 # 03 Y:2003 | 03 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $940 | $1,106 | Not Implemented |
GT0765 # 04 Y:2003 | 04 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,180 | $6,000 | Implemented |
GT0765 # 05 Y:2003 | 05 | 2003 | USE MINIMUM STEAM OPERATING PRESSURE | $750 | $0 | Not Implemented |
AS0344 # 02 Y:2003 | 02 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $512 | $5,250 | Not Implemented |
AS0344 # 07 Y:2003 | 07 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,260 | $1,751 | n/a |
AS0344 # 06 Y:2003 | 06 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $68 | $167 | Implemented |
AS0344 # 05 Y:2003 | 05 | 2003 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $82 | $356 | Implemented |
AS0344 # 04 Y:2003 | 04 | 2003 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $473 | $21 | Implemented |
AS0344 # 03 Y:2003 | 03 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,587 | $10,835 | Implemented |
AS0344 # 01 Y:2003 | 01 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,169 | $6,136 | Implemented |
OR0426 # 01 Y:2003 | 01 | 2003 | ADJUST BURNERS FOR EFFICIENT OPERATION | $104,400 | $150 | Implemented |
OR0426 # 02 Y:2003 | 02 | 2003 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $6,010 | $135 | Implemented |
OR0426 # 03 Y:2003 | 03 | 2003 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $1,720 | $1,000 | Implemented |
OR0426 # 04 Y:2003 | 04 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $41,000 | $41,000 | Implemented |
OR0426 # 05 Y:2003 | 05 | 2003 | SIZE AIR HANDLING GRILLS/ DUCT/S COILS TO MINIMIZE AIR RESISTANCE | $9,530 | $73,800 | Not Implemented |
OR0426 # 06 Y:2003 | 06 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,570 | $6,080 | Not Implemented |
OR0426 # 07 Y:2003 | 07 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $199 | $0 | Implemented |