Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
35
matching recommendationsNAICS | 3221 | Pulp, Paper, and Paperboard Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS1917 # 05 Y:2019 | 05 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $132,076 | $93,000 | Not Implemented |
LS1917 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,391 | $0 | Implemented |
LS1917 # 03 Y:2019 | 03 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,748 | $535 | Not Implemented |
LS1917 # 02 Y:2019 | 02 | 2019 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,335 | $175 | Not Implemented |
LS1917 # 01 Y:2019 | 01 | 2019 | PAY UTILITY BILLS ON TIME | $27,657 | $0 | Implemented |
LS1917 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,652 | $49,919 | Implemented |
AM0787 # 02 Y:2019 | 02 | 2019 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $312,044 | $849,614 | Not Implemented |
AM0787 # 04 Y:2019 | 04 | 2019 | USE SYNTHETIC LUBRICANT | $13,271 | $14,560 | Implemented |
AM0787 # 03 Y:2019 | 03 | 2019 | REPAIR OR REPLACE STEAM TRAPS | $56,595 | $10,440 | Implemented |
AM0787 # 01 Y:2019 | 01 | 2019 | USE STEAM PRESSURE REDUCTION TO GENERATE POWER | $290,927 | $1,011,274 | Not Implemented |
AM0787 # 05 Y:2019 | 05 | 2019 | OPTIMIZE PLANT POWER FACTOR | $70,814 | $178,864 | Implemented |
AM0787 # 07 Y:2019 | 07 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,577 | $2,640 | Implemented |
AM0787 # 06 Y:2019 | 06 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,322 | $825 | Implemented |
AM0787 # 08 Y:2019 | 08 | 2019 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $399 | $280 | Not Implemented |
WV0580 # 02 Y:2019 | 02 | 2019 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $143,962 | $6,000 | Implemented |
WV0580 # 06 Y:2019 | 06 | 2019 | REPAIR OR REPLACE STEAM TRAPS | $1,791 | $5,731 | Implemented |
WV0580 # 05 Y:2019 | 05 | 2019 | INSULATE BARE EQUIPMENT | $2,238 | $2,550 | Implemented |
WV0580 # 04 Y:2019 | 04 | 2019 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,437 | $15,360 | Implemented |
WV0580 # 03 Y:2019 | 03 | 2019 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $52,590 | $160,314 | Not Implemented |
WV0580 # 01 Y:2019 | 01 | 2019 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $265,061 | $31,000 | Not Implemented |
AS0470 # 01 Y:2019 | 01 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $680,774 | $3,152,400 | Implemented |
AS0470 # 02 Y:2019 | 02 | 2019 | UPGRADE CONTROLS ON COMPRESSORS | $19,947 | $40,400 | Implemented |
AS0470 # 03 Y:2019 | 03 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $19,843 | $10,895 | Implemented |
AS0470 # 04 Y:2019 | 04 | 2019 | REPAIR AND ELIMINATE STEAM LEAKS | $12,345 | $516 | Implemented |
AS0470 # 05 Y:2019 | 05 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,823 | $3,204 | Implemented |