Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
222
matching recommendationsNAICS | 32229 | Other Converted Paper Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UK1704 # 02 Y:2017 | 02 | 2017 | OPTIMIZE PLANT POWER FACTOR | $15,401 | $43,120 | Implemented |
UK1704 # 01 Y:2017 | 01 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $35,480 | $18,700 | Implemented |
IP0056 # 14 Y:2016 | 14 | 2016 | OPTIMIZE PLANT POWER FACTOR | $14,198 | $22,745 | Not Implemented |
IP0056 # 15 Y:2016 | 15 | 2016 | APPLY FOR INVESTMENT INCENTIVES | $1,896 | $5,000 | Not Implemented |
IP0056 # 13 Y:2016 | 13 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,149 | $51,579 | Not Implemented |
IP0056 # 12 Y:2016 | 12 | 2016 | APPLY FOR INVESTMENT INCENTIVES | $5,810 | $5,000 | Not Implemented |
IP0056 # 11 Y:2016 | 11 | 2016 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,064 | $6,597 | Not Implemented |
IP0056 # 10 Y:2016 | 10 | 2016 | INSTALL OCCUPANCY SENSORS | $311 | $218 | Implemented |
IP0056 # 09 Y:2016 | 09 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,909 | $1,267 | Not Implemented |
IP0056 # 08 Y:2016 | 08 | 2016 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $3,273 | $2,406 | Not Implemented |
IP0056 # 07 Y:2016 | 07 | 2016 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $356 | $170 | Not Implemented |
IP0056 # 06 Y:2016 | 06 | 2016 | APPLY FOR INVESTMENT INCENTIVES | $29,356 | $10,000 | Not Implemented |
IP0056 # 05 Y:2016 | 05 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,870 | $300 | Implemented |
IP0056 # 03 Y:2016 | 03 | 2016 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,361 | $0 | Implemented |
IP0056 # 02 Y:2016 | 02 | 2016 | PAY BILLS ON TIME TO AVOID LATE FEES | $1,368 | $0 | Implemented |
IP0056 # 01 Y:2016 | 01 | 2016 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $1,612 | $0 | Not Implemented |
IP0056 # 04 Y:2016 | 04 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,759 | $165 | Implemented |
MI0288 # 02 Y:2015 | 02 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $19,212 | $1,670 | Implemented |
MI0288 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,939 | $91,936 | Implemented |
MI0288 # 04 Y:2015 | 04 | 2015 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $9,840 | $4,691 | Implemented |
MI0288 # 05 Y:2015 | 05 | 2015 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,547 | $280 | Not Implemented |
MI0288 # 06 Y:2015 | 06 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,388 | $40 | Implemented |
MI0288 # 07 Y:2015 | 07 | 2015 | USE OPTIMUM THICKNESS INSULATION | $5,040 | $1,810 | Not Implemented |
MI0288 # 08 Y:2015 | 08 | 2015 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $4,441 | $3,140 | Not Implemented |
MI0288 # 10 Y:2015 | 10 | 2015 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,706 | $1,300 | Implemented |