IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

20

matching recommendations
Reset
NAICS 323 Printing and Related Support Activities
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CC0013 # 02 Y:2023 02 2023 TURN OFF EQUIPMENT WHEN NOT IN USE $1,363 $0 n/a
CC0013 # 03 Y:2023 03 2023 HEAT WATER DURING OFF-PEAK PERIODS AND STORE FOR LATER USE $4,697 $8,400 n/a
CC0013 # 04 Y:2023 04 2023 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION $21,990 $40,000 n/a
CC0013 # 05 Y:2023 05 2023 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $33,597 $180,600 n/a
CC0013 # 01 Y:2023 01 2023 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,074 $0 n/a
CL2006 # 02 Y:2020 02 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $13,133 $4,500 Implemented
CL2006 # 05 Y:2020 05 2020 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $4,314 $3,400 Implemented
CL2006 # 04 Y:2020 04 2020 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $5,769 $12,768 Not Implemented
CL2006 # 03 Y:2020 03 2020 MODIFY STARTUP/SHUTDOWN TIMES $7,541 $1,000 Not Implemented
CL2006 # 01 Y:2020 01 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $41,598 $51,573 Implemented
CL1906 # 04 Y:2019 04 2019 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $816 $574 Implemented
CL1906 # 03 Y:2019 03 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,979 $1,440 Implemented
CL1906 # 02 Y:2019 02 2019 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $694 $0 Implemented
CL1906 # 01 Y:2019 01 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,464 $12,357 Implemented
CL1701 # 01 Y:2017 01 2017 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $36,942 $10,000 Implemented
CL1701 # 02 Y:2017 02 2017 INSTALL TIMERS AND/OR THERMOSTATS $18,050 $250 Not Implemented
CL1701 # 03 Y:2017 03 2017 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN $12,535 $3,650 Implemented
CL1701 # 04 Y:2017 04 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $11,647 $22,515 Implemented
CL1701 # 05 Y:2017 05 2017 INSTALL WASTE HEAT BOILER TO PROVIDE DIRECT POWER $5,838 $13,500 Implemented
CL1701 # 06 Y:2017 06 2017 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $4,382 $6,000 Not Implemented