Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,874
matching recommendationsNAICS | 32311 | Printing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0242 # 05 Y:2004 | 05 | 2004 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $3,122 | $300 | Not Implemented |
MS0242 # 06 Y:2004 | 06 | 2004 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,170 | $371 | Not Implemented |
MS0242 # 07 Y:2004 | 07 | 2004 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,381 | $0 | Not Implemented |
MS0242 # 08 Y:2004 | 08 | 2004 | PAY BILLS ON TIME TO AVOID LATE FEES | $753 | $234 | Not Implemented |
MS0242 # 09 Y:2004 | 09 | 2004 | USE PHOTOCELL CONTROLS | $470 | $222 | Not Implemented |
MS0242 # 10 Y:2004 | 10 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $297 | $48 | Not Implemented |
MS0242 # 11 Y:2004 | 11 | 2004 | APPLY FOR INVESTMENT INCENTIVES | $48 | $50 | Not Implemented |
UF0332 # 01 Y:2003 | 01 | 2003 | INSTALL DESICCANT HUMIDITY CONTROL SYSTEM | $20,678 | $12,800 | Not Implemented |
UF0332 # 02 Y:2003 | 02 | 2003 | REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT | $15,627 | $1,500 | Not Implemented |
UF0332 # 03 Y:2003 | 03 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $676 | $803 | Implemented |
UF0332 # 04 Y:2003 | 04 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,350 | $4,928 | Not Implemented |
UF0332 # 05 Y:2003 | 05 | 2003 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,090 | $1,060 | Implemented |
UF0332 # 06 Y:2003 | 06 | 2003 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $6,954 | $42,000 | Implemented |
UU0052 # 01 Y:2003 | 01 | 2003 | OPTIMIZE PLANT POWER FACTOR | $12,731 | $22,600 | n/a |
UU0052 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,035 | $134 | n/a |
UU0052 # 03 Y:2003 | 03 | 2003 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,186 | $2,810 | n/a |
UU0052 # 04 Y:2003 | 04 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,302 | $1,661 | n/a |
UU0052 # 05 Y:2003 | 05 | 2003 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,027 | $6,000 | n/a |
UU0052 # 06 Y:2003 | 06 | 2003 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,237 | $410 | n/a |
UU0052 # 07 Y:2003 | 07 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $392 | $594 | n/a |
UU0052 # 08 Y:2003 | 08 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,664 | $3,366 | n/a |
UU0052 # 09 Y:2003 | 09 | 2003 | RECOVER AND REUSE WASTE MATERIAL | $50 | $0 | n/a |
WI0450 # 01 Y:2003 | 01 | 2003 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $137,202 | $84,000 | Not Implemented |
WI0450 # 02 Y:2003 | 02 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $64,456 | $144,540 | n/a |
WI0450 # 03 Y:2003 | 03 | 2003 | UPGRADE CONTROLS ON COMPRESSORS | $10,369 | $22,000 | Not Implemented |