Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,548
matching recommendationsNAICS | 325 | Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1089 # 05 Y:2024 | 05 | 2024 | INSTALL OCCUPANCY SENSORS | $472 | $550 | n/a |
UD1089 # 04 Y:2024 | 04 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $7,169 | $2,030 | n/a |
UD1089 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,974 | $0 | n/a |
UD1089 # 02 Y:2024 | 02 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $30,384 | $0 | n/a |
UD1089 # 01 Y:2024 | 01 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $79,860 | $0 | n/a |
LS2414 # 05 Y:2024 | 05 | 2024 | REPLACE BOILER | $58,575 | $420,000 | n/a |
LS2414 # 04 Y:2024 | 04 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $810,158 | $2,364,120 | n/a |
LS2414 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,889 | $1,050 | n/a |
LS2414 # 02 Y:2024 | 02 | 2024 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $265,645 | $63,000 | n/a |
LS2414 # 01 Y:2024 | 01 | 2024 | INSTALL OCCUPANCY SENSORS | $2,180 | $250 | n/a |
UU0255 # 08 Y:2024 | 08 | 2024 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $6,932 | $60,862 | n/a |
UU0255 # 07 Y:2024 | 07 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,849 | $4,680 | n/a |
UU0255 # 06 Y:2024 | 06 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,033 | $8,000 | n/a |
UU0255 # 05 Y:2024 | 05 | 2024 | INSTALL OCCUPANCY SENSORS | $1,750 | $4,964 | n/a |
UU0255 # 04 Y:2024 | 04 | 2024 | USE OPTIMUM THICKNESS INSULATION | $10,948 | $4,085 | n/a |
UU0255 # 03 Y:2024 | 03 | 2024 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,299 | $2,614 | n/a |
UU0255 # 02 Y:2024 | 02 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $5,674 | $8,711 | n/a |
UU0255 # 01 Y:2024 | 01 | 2024 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $64,548 | $8,000 | n/a |
MI0445 # 08 Y:2024 | 08 | 2024 | INSTALL OCCUPANCY SENSORS | $3,269 | $2,860 | n/a |
MI0445 # 07 Y:2024 | 07 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,583 | $5,793 | n/a |
MI0445 # 06 Y:2024 | 06 | 2024 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $19,584 | $150 | n/a |
MI0445 # 05 Y:2024 | 05 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $32,574 | $11,027 | n/a |
MI0445 # 04 Y:2024 | 04 | 2024 | OPTIMIZE PLANT POWER FACTOR | $46,588 | $99,444 | n/a |
MI0445 # 03 Y:2024 | 03 | 2024 | PAY UTILITY BILLS ON TIME | $80,165 | $0 | n/a |
MI0445 # 02 Y:2024 | 02 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $217,248 | $42,472 | n/a |