Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
219
matching recommendationsNAICS | 325 | Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UL2507 # 03 Y:2025 | 03 | 2025 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $16,032 | $37,000 | n/a |
UL2507 # 01 Y:2025 | 01 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $56,773 | $527,158 | n/a |
UL2507 # 02 Y:2025 | 02 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,632 | $24,675 | n/a |
UF0632 # 02 Y:2025 | 02 | 2025 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $21,772 | $20,202 | n/a |
UF0632 # 03 Y:2025 | 03 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,911 | $34,076 | n/a |
UF0632 # 06 Y:2025 | 06 | 2025 | IMPROVE COMBUSTION CONTROL CAPABILITY | $4,200 | $2,000 | n/a |
UF0632 # 05 Y:2025 | 05 | 2025 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $5,526 | $20,560 | n/a |
UF0632 # 04 Y:2025 | 04 | 2025 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $12,726 | $12,000 | n/a |
UF0632 # 08 Y:2025 | 08 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,170 | $2,654 | n/a |
UF0632 # 13 Y:2025 | 13 | 2025 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $1,094 | $0 | n/a |
UF0632 # 12 Y:2025 | 12 | 2025 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $7,429 | $20,000 | n/a |
UF0632 # 07 Y:2025 | 07 | 2025 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $4,170 | $6,785 | n/a |
UF0632 # 01 Y:2025 | 01 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $43,631 | $322,608 | n/a |
UF0632 # 10 Y:2025 | 10 | 2025 | INSTALL DE-AERATOR IN PLACE OF CONDENSATE TANK | $2,684 | $2,743 | n/a |
UF0632 # 09 Y:2025 | 09 | 2025 | INSTALL TURBULATORS | $2,277 | $3,750 | n/a |
UF0632 # 11 Y:2025 | 11 | 2025 | USE REVERSE OSMOSIS TO CONCENTRATE MATERIAL | $3,839 | $3,079 | n/a |
UF0632 # 14 Y:2025 | 14 | 2025 | IMPROVE SPACE COMFORT CONDITIONING | $1,115 | $3,888 | n/a |
UL2506 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,455 | $2,940 | n/a |
UL2506 # 03 Y:2025 | 03 | 2025 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $43,343 | $86,469 | n/a |
UL2506 # 04 Y:2025 | 04 | 2025 | OPTIMIZE PLANT POWER FACTOR | $49,775 | $25,480 | n/a |
UL2506 # 06 Y:2025 | 06 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,323 | $17,116 | n/a |
UL2506 # 05 Y:2025 | 05 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $13,709 | $151,700 | n/a |
UL2506 # 01 Y:2025 | 01 | 2025 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $77,396 | $40,000 | n/a |
WV0682 # 01 Y:2025 | 01 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $98,686 | $61,240 | n/a |
WV0682 # 02 Y:2025 | 02 | 2025 | MINIMIZE WATER USAGE | $71,374 | $60,060 | n/a |