Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
13
matching recommendationsNAICS | 325130 | Synthetic Dye and Pigment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0306 # 01 Y:2006 | 01 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,385 | $2,500 | Implemented |
UM0306 # 02 Y:2006 | 02 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $11,812 | $22,458 | Not Implemented |
UM0306 # 03 Y:2006 | 03 | 2006 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,934 | $2,500 | Not Implemented |
UM0306 # 04 Y:2006 | 04 | 2006 | ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA | $8,336 | $7,520 | Implemented |
UM0306 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,571 | $9,421 | Implemented |
UM0306 # 06 Y:2006 | 06 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,482 | $2,429 | Not Implemented |
UM0306 # 07 Y:2006 | 07 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,558 | $197 | Implemented |
UM0243 # 01 Y:2003 | 01 | 2003 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $142,452 | $31,500 | Implemented |
UM0243 # 02 Y:2003 | 02 | 2003 | INSULATE BARE EQUIPMENT | $20,715 | $4,565 | Not Implemented |
UM0243 # 03 Y:2003 | 03 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $24,928 | $520 | Implemented |
UM0243 # 04 Y:2003 | 04 | 2003 | AIR CONDITION ONLY SPACE NECESSARY | $13,955 | $6,000 | Implemented |
UM0243 # 05 Y:2003 | 05 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,857 | $150 | Implemented |
UM0243 # 06 Y:2003 | 06 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,082 | $100 | Not Implemented |