Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
376
matching recommendationsNAICS | 325180 | Other Basic Inorganic Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0062 # 10 Y:2011 | 10 | 2011 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $84,900 | $45,000 | Not Implemented |
TT0062 # 11 Y:2011 | 11 | 2011 | REPLACE DIRECT FIRED WITH STEAM HEAT | $78,600 | $30,000 | Implemented |
TT0062 # 12 Y:2011 | 12 | 2011 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $34,000 | $30,000 | Not Implemented |
UA3010 # 01 Y:2011 | 01 | 2011 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $361,004 | $66,433 | Not Implemented |
UA3010 # 02 Y:2011 | 02 | 2011 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,810 | $17,030 | Implemented |
UA3010 # 03 Y:2011 | 03 | 2011 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,140 | $2,925 | Implemented |
UA3010 # 04 Y:2011 | 04 | 2011 | USE RADIANT HEATER FOR SPOT HEATING | $871 | $1,836 | Not Implemented |
UA3010 # 05 Y:2011 | 05 | 2011 | INSTALL TIMERS AND/OR THERMOSTATS | $1,130 | $397 | Implemented |
UA3010 # 06 Y:2011 | 06 | 2011 | INSULATE BARE EQUIPMENT | $6,592 | $499 | Not Implemented |
UA3010 # 07 Y:2011 | 07 | 2011 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $18,662 | $50,000 | Not Implemented |
WV0403 # 06 Y:2010 | 06 | 2010 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,610 | $8,756 | Not Implemented |
WV0403 # 11 Y:2010 | 11 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,180 | $748 | Implemented |
WV0403 # 10 Y:2010 | 10 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,238 | $110 | Implemented |
WV0403 # 09 Y:2010 | 09 | 2010 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,274 | $1,620 | Implemented |
WV0403 # 08 Y:2010 | 08 | 2010 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,342 | $10,700 | Not Implemented |
WV0403 # 07 Y:2010 | 07 | 2010 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $2,357 | $8,600 | Not Implemented |
WV0403 # 05 Y:2010 | 05 | 2010 | USE RADIANT HEATER FOR SPOT HEATING | $4,543 | $20,500 | Not Implemented |
WV0403 # 04 Y:2010 | 04 | 2010 | IMPROVE LUBRICATION PRACTICES | $9,486 | $5,823 | Not Implemented |
WV0403 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,231 | $70,410 | Implemented |
WV0403 # 02 Y:2010 | 02 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,050 | $52,453 | Implemented |
WV0403 # 01 Y:2010 | 01 | 2010 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $45,685 | $55,000 | Implemented |
CO0635 # 01 Y:2010 | 01 | 2010 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $21,490 | $12,290 | Not Implemented |
CO0635 # 02 Y:2010 | 02 | 2010 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,520 | $10,350 | Not Implemented |
CO0635 # 03 Y:2010 | 03 | 2010 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,100 | $1,510 | Not Implemented |
CO0635 # 04 Y:2010 | 04 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,170 | $11,190 | Not Implemented |