Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
390
matching recommendationsNAICS | 325199 | All Other Basic Organic Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UC2419 # 02 Y:2024 | 02 | 2024 | PAY UTILITY BILLS ON TIME | $178 | $0 | n/a |
UC2419 # 05 Y:2024 | 05 | 2024 | INSTALL / REPAIR INSULATION ON STEAM LINES | $7,234 | $1,183 | n/a |
UC2419 # 08 Y:2024 | 08 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $436 | $75 | n/a |
UC2419 # 06 Y:2024 | 06 | 2024 | INSULATE BARE EQUIPMENT | $22,646 | $4,752 | n/a |
UC2419 # 03 Y:2024 | 03 | 2024 | OPTIMIZE PLANT POWER FACTOR | $6,548 | $10,295 | n/a |
IC0313 # 01 Y:2024 | 01 | 2024 | OPTIMIZE OPERATION OF MULTI-STAGE VACUUM STEAM JETS | $9,651 | $7,079 | Implemented |
IC0313 # 11 Y:2024 | 11 | 2024 | INSULATE BARE EQUIPMENT | $4,631 | $8,869 | Implemented |
IC0313 # 08 Y:2024 | 08 | 2024 | ADOPT IN-HOUSE MATERIAL GENERATION | $75,451 | $92,231 | Not Implemented |
IC0313 # 10 Y:2024 | 10 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,979 | $2,430 | Implemented |
IC0313 # 09 Y:2024 | 09 | 2024 | REPAIR AND ELIMINATE STEAM LEAKS | $19,590 | $704 | Implemented |
IC0313 # 06 Y:2024 | 06 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,557 | $0 | Implemented |
IC0313 # 07 Y:2024 | 07 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $10,223 | $100,000 | Not Implemented |
IC0313 # 05 Y:2024 | 05 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $6,524 | $27,807 | Not Implemented |
IC0313 # 03 Y:2024 | 03 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $24,211 | $220,985 | Not Implemented |
IC0313 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,562 | $0 | Implemented |
IC0313 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,107 | $6,125 | Not Implemented |
CC0039 # 05 Y:2024 | 05 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $21,466 | $68,475 | n/a |
CC0039 # 01 Y:2024 | 01 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,082 | $7,780 | n/a |
CC0039 # 02 Y:2024 | 02 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $8,467 | $0 | n/a |
CC0039 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $718 | $1,000 | n/a |
CC0039 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,557 | $5,600 | n/a |
CC0039 # 09 Y:2024 | 09 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $23,248 | $226,305 | n/a |
CC0039 # 08 Y:2024 | 08 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $878 | $2,642 | n/a |
CC0039 # 07 Y:2024 | 07 | 2024 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $2,905 | $0 | n/a |
CC0039 # 06 Y:2024 | 06 | 2024 | REDUCE EXCESS STEAM BLEEDING | $11,803 | $0 | n/a |