Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
57
matching recommendationsNAICS | 32599 | All Other Chemical Product and Preparation Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0661 # 02 Y:2024 | 02 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $1,321,862 | $54,390 | n/a |
SD0661 # 11 Y:2024 | 11 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $970 | $1,863 | n/a |
SD0661 # 10 Y:2024 | 10 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,652 | $2,148 | n/a |
SD0661 # 13 Y:2024 | 13 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,043 | $19,842 | n/a |
SD0661 # 12 Y:2024 | 12 | 2024 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $12,725 | $11,775 | n/a |
SD0661 # 08 Y:2024 | 08 | 2024 | ADOPT IN-HOUSE MATERIAL GENERATION | $809,075 | $47,546 | n/a |
SD0661 # 07 Y:2024 | 07 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $854 | $250 | n/a |
SD0661 # 06 Y:2024 | 06 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,354 | $0 | n/a |
SD0661 # 05 Y:2024 | 05 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $10,205 | $0 | n/a |
SD0661 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,348 | $676 | n/a |
SD0661 # 09 Y:2024 | 09 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,243 | $7,340 | n/a |
SD0661 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $641,754 | $589,764 | n/a |
SD0661 # 04 Y:2024 | 04 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $3,584 | $4,191 | n/a |
SJ0008 # 04 Y:2023 | 04 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $126 | $436 | Not Implemented |
SJ0008 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $13,195 | $77,365 | Not Implemented |
SJ0008 # 02 Y:2023 | 02 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $365 | $0 | Implemented |
SJ0008 # 03 Y:2023 | 03 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $80 | $0 | Not Implemented |
SJ0008 # 05 Y:2023 | 05 | 2023 | INSULATE BARE EQUIPMENT | $265 | $344 | Implemented |
SJ0008 # 06 Y:2023 | 06 | 2023 | INSTALL OCCUPANCY SENSORS | $78 | $177 | Not Implemented |
SD0548 # 07 Y:2017 | 07 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,113 | $1,500 | Implemented |
SD0548 # 08 Y:2017 | 08 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,052 | $360 | Implemented |
SD0548 # 06 Y:2017 | 06 | 2017 | INSTALL OCCUPANCY SENSORS | $2,573 | $5,317 | Implemented |
SD0548 # 01 Y:2017 | 01 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,809 | $47,543 | Implemented |
SD0548 # 02 Y:2017 | 02 | 2017 | USE PHOTOCELL CONTROLS | $4,954 | $5,368 | Implemented |
SD0548 # 03 Y:2017 | 03 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,317 | $7,500 | Not Implemented |