IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

10

matching recommendations
Reset
NAICS 325998 All Other Miscellaneous Chemical Product and Preparation Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CC0002 # 01 Y:2022 01 2022 RECOVER WASTE HEAT FROM EQUIPMENT $2,068 $3,800 n/a
CC0002 # 02 Y:2022 02 2022 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,965 $2,800 n/a
CC0002 # 03 Y:2022 03 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $954 $0 n/a
CC0002 # 04 Y:2022 04 2022 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $106 $180 n/a
MI0404 # 01 Y:2022 01 2022 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $28,220 $580 Implemented
MI0404 # 02 Y:2022 02 2022 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $9,764 $479 Not Implemented
MI0404 # 03 Y:2022 03 2022 METER WASTE WATER $8,108 $1,533 Implemented
MI0404 # 04 Y:2022 04 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,549 $1,660 Not Implemented
MI0404 # 05 Y:2022 05 2022 REDUCE EXCESSIVE BOILER BLOWDOWN $1,720 $2,088 Not Implemented
MI0404 # 06 Y:2022 06 2022 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,392 $2,520 Not Implemented