Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,714
matching recommendationsNAICS | 326 | Plastics and Rubber Products Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0583 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $87,396 | $642,159 | Not Implemented |
AS0583 # 02 Y:2024 | 02 | 2024 | ADD AIR SHIELDS TO TRUCKS TO INCREASE FUEL MILEAGE | $43,888 | $15,124 | Not Implemented |
AS0583 # 03 Y:2024 | 03 | 2024 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $4,022 | $1,805 | Not Implemented |
AS0583 # 04 Y:2024 | 04 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,282 | $4,696 | Not Implemented |
AS0583 # 05 Y:2024 | 05 | 2024 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $137 | $172 | Not Implemented |
AS0583 # 06 Y:2024 | 06 | 2024 | INSTALL OCCUPANCY SENSORS | $122 | $476 | Not Implemented |
AS0583 # 07 Y:2024 | 07 | 2024 | INSTALL SPECTRAL REFLECTORS / DELAMP | $94 | $52 | Not Implemented |
MI0446 # 01 Y:2024 | 01 | 2024 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $103,738 | $390,000 | n/a |
MI0446 # 02 Y:2024 | 02 | 2024 | UPGRADE CONVEYORS | $36,000 | $40,966 | n/a |
MI0446 # 03 Y:2024 | 03 | 2024 | ESTABLISH A PREVENTATIVE MAINTENANCE PROGRAM | $15,109 | $12,480 | n/a |
IP0197 # 01 Y:2024 | 01 | 2024 | USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR | $33,478 | $697 | Implemented |
IP0197 # 02 Y:2024 | 02 | 2024 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,662 | $320 | Not Implemented |
IP0197 # 03 Y:2024 | 03 | 2024 | INSTALL OCCUPANCY SENSORS | $1,000 | $1,506 | Implemented |
IP0197 # 04 Y:2024 | 04 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $8,370 | $13,000 | Implemented |
IP0197 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,867 | $18,107 | Implemented |
TT0313 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,143 | $60 | Implemented |
TT0313 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $34,255 | $2,625 | Implemented |
TT0313 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $4,207 | $340 | Implemented |
TT0313 # 04 Y:2024 | 04 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $21,724 | $2,600 | Implemented |
TT0313 # 05 Y:2024 | 05 | 2024 | INSULATE BARE EQUIPMENT | $640 | $87 | Not Implemented |
TT0313 # 06 Y:2024 | 06 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,134 | $3,000 | Not Implemented |
TT0313 # 07 Y:2024 | 07 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $29,164 | $15,000 | Not Implemented |
TT0313 # 08 Y:2024 | 08 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,284 | $1,200 | Not Implemented |
TT0313 # 09 Y:2024 | 09 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $14,234 | $9,800 | Not Implemented |
TT0313 # 10 Y:2024 | 10 | 2024 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $261,275 | $200,000 | Not Implemented |