Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,415
matching recommendationsNAICS | 326 | Plastics and Rubber Products Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0570 # 11 Y:2010 | 11 | 2010 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $521 | $490 | Implemented |
AM0570 # 12 Y:2010 | 12 | 2010 | PAY BILLS ON TIME TO AVOID LATE FEES | $120 | $0 | Implemented |
DL0046 # 01 Y:2010 | 01 | 2010 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,503 | $0 | Not Implemented |
DL0046 # 02 Y:2010 | 02 | 2010 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,940 | $0 | Not Implemented |
DL0046 # 03 Y:2010 | 03 | 2010 | INSULATE BARE EQUIPMENT | $7,292 | $520 | Not Implemented |
DL0046 # 04 Y:2010 | 04 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,168 | $1,500 | Implemented |
DL0046 # 05 Y:2010 | 05 | 2010 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $7,619 | $10,000 | Implemented |
DL0046 # 06 Y:2010 | 06 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,295 | $23,738 | Implemented |
DL0046 # 07 Y:2010 | 07 | 2010 | DE-ENERGIZE EXCESS TRANSFORMER CAPACITY | $785 | $2,410 | Not Implemented |
BD0368 # 01 Y:2010 | 01 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,866 | $25,159 | Implemented |
BD0368 # 02 Y:2010 | 02 | 2010 | INSTALL OCCUPANCY SENSORS | $1,960 | $750 | Not Implemented |
BD0368 # 03 Y:2010 | 03 | 2010 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $329 | $410 | Implemented |
BD0368 # 04 Y:2010 | 04 | 2010 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,981 | $7,700 | Not Implemented |
BD0368 # 05 Y:2010 | 05 | 2010 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,297 | $2,500 | Not Implemented |
BD0368 # 06 Y:2010 | 06 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,857 | $0 | Implemented |
SD0424 # 01 Y:2010 | 01 | 2010 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $67,934 | $1,710 | Implemented |
SD0424 # 02 Y:2010 | 02 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $41,306 | $7,308 | Implemented |
SD0424 # 03 Y:2010 | 03 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,177 | $4,500 | Implemented |
SD0424 # 04 Y:2010 | 04 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $41,138 | $14,750 | Not Implemented |
SD0424 # 05 Y:2010 | 05 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,815 | $16,270 | Not Implemented |
SD0424 # 06 Y:2010 | 06 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,490 | $10,074 | Not Implemented |
SD0424 # 07 Y:2010 | 07 | 2010 | OPTIMIZE PLANT POWER FACTOR | $8,162 | $31,629 | Not Implemented |
MZ0045 # 01 Y:2009 | 01 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,876 | $46,050 | Implemented |
MZ0045 # 02 Y:2009 | 02 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,746 | $4,200 | Not Implemented |
MZ0045 # 03 Y:2009 | 03 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,734 | $950 | Implemented |