Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
15
matching recommendationsNAICS | 326121 | Unlaminated Plastics Profile Shape Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0934 # 01 Y:2016 | 01 | 2016 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $27,456 | $25,000 | Not Implemented |
OK0934 # 02 Y:2016 | 02 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,615 | $915 | Not Implemented |
OK0934 # 03 Y:2016 | 03 | 2016 | ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA | $134,039 | $1,300 | Implemented |
OK0934 # 04 Y:2016 | 04 | 2016 | INSULATE BARE EQUIPMENT | $63,243 | $3,161 | Implemented |
OK0934 # 05 Y:2016 | 05 | 2016 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $11,990 | $0 | Not Implemented |
OK0934 # 06 Y:2016 | 06 | 2016 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $8,069 | $10,000 | Not Implemented |
LL0266 # 01 Y:2007 | 01 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $42,563 | $14,000 | Implemented |
LL0266 # 02 Y:2007 | 02 | 2007 | INSULATE BARE EQUIPMENT | $21,291 | $1,905 | Implemented |
LL0266 # 03 Y:2007 | 03 | 2007 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $9,193 | $795 | Not Implemented |
LL0266 # 04 Y:2007 | 04 | 2007 | INSTALL OCCUPANCY SENSORS | $5,235 | $1,680 | Not Implemented |
LL0266 # 05 Y:2007 | 05 | 2007 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,916 | $378 | Not Implemented |
LL0266 # 06 Y:2007 | 06 | 2007 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $492 | $942 | Not Implemented |
LL0266 # 07 Y:2007 | 07 | 2007 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $528 | $1,023 | Not Implemented |
LL0266 # 08 Y:2007 | 08 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $371 | $280 | Not Implemented |
LL0266 # 09 Y:2007 | 09 | 2007 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,920 | $1,325 | Not Implemented |