Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,797
matching recommendationsNAICS | 326199 | All Other Plastics Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0736 # 05 Y:2017 | 05 | 2017 | PAY UTILITY BILLS ON TIME | $1,617 | $0 | Implemented |
AM0736 # 06 Y:2017 | 06 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,600 | $300 | Implemented |
AM0736 # 07 Y:2017 | 07 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,550 | $2,000 | Implemented |
AM0736 # 08 Y:2017 | 08 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,390 | $390 | Implemented |
AM0736 # 09 Y:2017 | 09 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $500 | $20 | Not Implemented |
UD0971 # 01 Y:2017 | 01 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,580 | $0 | Implemented |
UD0971 # 02 Y:2017 | 02 | 2017 | USE MINIMUM STEAM OPERATING PRESSURE | $10,210 | $50 | Not Implemented |
UD0971 # 03 Y:2017 | 03 | 2017 | COVER OPEN TANKS | $8,336 | $2,760 | Not Implemented |
UD0971 # 04 Y:2017 | 04 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $972 | $50 | Implemented |
UD0971 # 05 Y:2017 | 05 | 2017 | ADD AREA LIGHTING SWITCHES | $2,213 | $500 | Not Implemented |
UD0971 # 06 Y:2017 | 06 | 2017 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $400 | $681 | Not Implemented |
UD0971 # 07 Y:2017 | 07 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,936 | $3,000 | Not Implemented |
UD0971 # 08 Y:2017 | 08 | 2017 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $51,180 | $3,650 | Not Implemented |
UD0971 # 09 Y:2017 | 09 | 2017 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $36,055 | $178,850 | Not Implemented |
UD0971 # 10 Y:2017 | 10 | 2017 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,985 | $22,000 | Not Implemented |
AS0442 # 01 Y:2017 | 01 | 2017 | UPGRADE CONTROLS ON COMPRESSORS | $25,870 | $7,794 | Not Implemented |
AS0442 # 02 Y:2017 | 02 | 2017 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $2,847 | $5,691 | Not Implemented |
AS0442 # 03 Y:2017 | 03 | 2017 | INSTALL OCCUPANCY SENSORS | $1,680 | $720 | Not Implemented |
MI0317 # 01 Y:2017 | 01 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $42,418 | $1,660 | Implemented |
MI0317 # 02 Y:2017 | 02 | 2017 | OPTIMIZE PLANT POWER FACTOR | $33,420 | $46,515 | Implemented |
MI0317 # 03 Y:2017 | 03 | 2017 | USE DIRECT AIR SUPPLY TO EXHAUST HOODS | $29,203 | $11,300 | Not Implemented |
MI0317 # 04 Y:2017 | 04 | 2017 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $18,556 | $8,294 | Implemented |
MI0317 # 05 Y:2017 | 05 | 2017 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $16,568 | $120 | Implemented |
MI0317 # 06 Y:2017 | 06 | 2017 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $6,683 | $1,885 | Implemented |
MI0317 # 07 Y:2017 | 07 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,154 | $2,140 | Not Implemented |