IAC Assessment: NC0602
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NC0602
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center North Carolina State
Assessment Year 2017
Principal Product Plastic parts
NAICS 326199 - All Other Plastics Product Manufacturing
SIC 3089 - Plastics Products, Nec
Sales $10,000,000-$50,000,000
# of Employees 250
Plant Area (Sq.Ft.) 130,000
Annual Production 30,000,000 Pieces
Production Hrs. Annual 6,000
Location (State) NC
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $307,864 5,274,795 kWh $0.06
Electricity Demand $50,754 11,712 kW-months/year $4.33
Natural Gas $15,018 1,727 MMBtu $8.70
TOTAL ENERGY COSTS $373,636
RECOMMENDED SAVINGS* $48,604 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$11,863
Cost:
$21,299
$8,710 149,150 $1,754 405 - - $1,399 - $8,710
149,150
kWh
$1,754
405
kW-months/year
-
-
$
$1,399
-
$
02: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$184
Cost:
$300
$184 3,150 - - - - - - $184
3,150
kWh
-
-
kW-months/year
-
-
$
-
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,747
Cost:
$200
$1,696 29,040 $251 58 $(-100) - $(-100) - $1,696
29,040
kWh
$251
58
kW-months/year
$(-100)
-
$
$(-100)
-
$
04: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$429
Cost:
$420
$429 7,350 - - - - - - $429
7,350
kWh
-
-
kW-months/year
-
-
$
-
-
$
05: 2.2511 INSULATE BARE EQUIPMENT Savings:
$831
Cost:
$3,467
$831 14,224 - - - - - - $831
14,224
kWh
-
-
kW-months/year
-
-
$
-
-
$
06: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$25,338
Cost:
$500
$25,338 - - - - - - - $25,338
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
07: 2.4151 DEVELOP A REPAIR/REPLACE POLICY Savings:
$8,212
Cost:
$14,854
$7,151 122,455 $1,061 245 - - - - $7,151
122,455
kWh
$1,061
245
kW-months/year
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$48,604
Cost:
$41,040
$44,339 325,369 $3,066 708 $(-100) - $1,299 - $44,339
325,369
kWh
$3,066
708
kW-months/year
$(-100)
-
$
$1,299
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost