Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2017 |
Principal Product | Plastic parts |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 130,000 |
Annual Production | 30,000,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $307,864 | 5,274,795 | kWh | $0.06 |
Electricity Demand | $50,754 | 11,712 | kW-months/year | $4.33 |
Natural Gas | $15,018 | 1,727 | MMBtu | $8.70 |
TOTAL ENERGY COSTS | $373,636 | |||
RECOMMENDED SAVINGS* | $48,604 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $11,863 Cost: $21,299 |
$8,710 | 149,150 | $1,754 | 405 | - | - | $1,399 | - |
$8,710 149,150 kWh |
$1,754 405 kW-months/year |
- - $ |
$1,399 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $184 Cost: $300 |
$184 | 3,150 | - | - | - | - | - | - |
$184 3,150 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,747 Cost: $200 |
$1,696 | 29,040 | $251 | 58 | $(-100) | - | $(-100) | - |
$1,696 29,040 kWh |
$251 58 kW-months/year |
$(-100) - $ |
$(-100) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $429 Cost: $420 |
$429 | 7,350 | - | - | - | - | - | - |
$429 7,350 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $831 Cost: $3,467 |
$831 | 14,224 | - | - | - | - | - | - |
$831 14,224 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $25,338 Cost: $500 |
$25,338 | - | - | - | - | - | - | - |
$25,338 - kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $8,212 Cost: $14,854 |
$7,151 | 122,455 | $1,061 | 245 | - | - | - | - |
$7,151 122,455 kWh |
$1,061 245 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $48,604 Cost: $41,040 |
$44,339 | 325,369 | $3,066 | 708 | $(-100) | - | $1,299 | - | $44,339 325,369 kWh |
$3,066 708 kW-months/year |
$(-100) - $ |
$1,299 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost |