IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

13

matching recommendations
Reset
NAICS 331 Primary Metal Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MA0593 # 01 Y:2006 01 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $43,728 $112,064 Implemented
MA0593 # 02 Y:2006 02 2006 TURN OFF EQUIPMENT WHEN NOT IN USE $39,365 $150 Implemented
MA0593 # 03 Y:2006 03 2006 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR $41,651 $69,000 Implemented
MA0593 # 04 Y:2006 04 2006 OPTIMIZE PLANT POWER FACTOR $32,612 $45,522 Implemented
MA0593 # 05 Y:2006 05 2006 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $23,990 $50,000 Implemented
MA0593 # 06 Y:2006 06 2006 REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY $16,246 $4,000 Implemented
MA0593 # 07 Y:2006 07 2006 REPAIR OR REPLACE STEAM TRAPS $15,042 $22,620 Implemented
MA0593 # 08 Y:2006 08 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $12,919 $170 Implemented
MA0593 # 09 Y:2006 09 2006 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $7,140 $6,500 Not Implemented
MA0593 # 10 Y:2006 10 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,718 $12,500 Implemented
MA0593 # 11 Y:2006 11 2006 INSULATE BARE EQUIPMENT $3,510 $3,010 Implemented
MA0593 # 12 Y:2006 12 2006 REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY $3,677 $1,639 Implemented
MA0593 # 13 Y:2006 13 2006 COVER OPEN TANKS $1,309 $1,470 Implemented