Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
999
matching recommendationsNAICS | 3312 | Steel Product Manufacturing from Purchased Steel |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0850 # 02 Y:2013 | 02 | 2013 | RECOVER WASTE HEAT FROM EQUIPMENT | $500 | $451 | Not Implemented |
OK0850 # 03 Y:2013 | 03 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $123 | $307 | Not Implemented |
OK0850 # 04 Y:2013 | 04 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $906 | $337 | Implemented |
OK0850 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,925 | $14,793 | Not Implemented |
OK0850 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $594 | $2,670 | Not Implemented |
OK0850 # 07 Y:2013 | 07 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $126 | $654 | Not Implemented |
OK0850 # 08 Y:2013 | 08 | 2013 | INSTALL TIMERS AND/OR THERMOSTATS | $2,079 | $159 | Not Implemented |
OK0850 # 09 Y:2013 | 09 | 2013 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $434 | $2,080 | Implemented |
OK0850 # 10 Y:2013 | 10 | 2013 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $212 | $1,200 | Not Implemented |
OK0850 # 11 Y:2013 | 11 | 2013 | OPTIMIZE PLANT POWER FACTOR | $2,693 | $11,638 | Not Implemented |
OK0850 # 12 Y:2013 | 12 | 2013 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $4,356 | $14,994 | Not Implemented |
BD0418 # 01 Y:2012 | 01 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $147,427 | $200,000 | Implemented |
BD0418 # 02 Y:2012 | 02 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $64,077 | $313,924 | Implemented |
BD0418 # 03 Y:2012 | 03 | 2012 | USE RADIANT HEATER FOR SPOT HEATING | $60,134 | $105,100 | Not Implemented |
BD0418 # 04 Y:2012 | 04 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $26,689 | $30,000 | Not Implemented |
BD0418 # 05 Y:2012 | 05 | 2012 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $23,015 | $48,000 | Not Implemented |
BD0418 # 06 Y:2012 | 06 | 2012 | USE PHOTOCELL CONTROLS | $18,400 | $14,100 | Implemented |
BD0418 # 07 Y:2012 | 07 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,842 | $6,000 | Not Implemented |
BD0418 # 08 Y:2012 | 08 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,441 | $600 | Implemented |
BD0418 # 09 Y:2012 | 09 | 2012 | INSTALL SKYLIGHTS | $5,048 | $12,215 | Implemented |
BD0418 # 10 Y:2012 | 10 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,117 | $20 | Implemented |
BD0418 # 11 Y:2012 | 11 | 2012 | INSTALL OCCUPANCY SENSORS | $2,653 | $1,200 | Implemented |
BD0418 # 12 Y:2012 | 12 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,527 | $500 | Implemented |
BD0418 # 13 Y:2012 | 13 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,210 | $1,500 | Implemented |
BD0418 # 14 Y:2012 | 14 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,121 | $1,225 | Implemented |