Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,058
matching recommendationsNAICS | 33231 | Plate Work and Fabricated Structural Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TA0121 # 03 Y:2006 | 03 | 2006 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $4,838 | $2,419 | Not Implemented |
TA0121 # 04 Y:2006 | 04 | 2006 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,770 | $1,770 | Not Implemented |
TA0120 # 01 Y:2006 | 01 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,165 | $200 | Not Implemented |
TA0120 # 02 Y:2006 | 02 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $839 | $0 | Not Implemented |
TA0120 # 03 Y:2006 | 03 | 2006 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $7,531 | $3,766 | Not Implemented |
TA0120 # 04 Y:2006 | 04 | 2006 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $24,151 | $0 | Not Implemented |
LL0260 # 01 Y:2006 | 01 | 2006 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $11,704 | $5,420 | Implemented |
LL0260 # 02 Y:2006 | 02 | 2006 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $7,890 | $5,109 | Not Implemented |
LL0260 # 03 Y:2006 | 03 | 2006 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,503 | $3,652 | Not Implemented |
LL0260 # 04 Y:2006 | 04 | 2006 | USE PHOTOCELL CONTROLS | $3,127 | $630 | Not Implemented |
LL0260 # 05 Y:2006 | 05 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,371 | $600 | Implemented |
LL0260 # 06 Y:2006 | 06 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,087 | $770 | Implemented |
LL0260 # 07 Y:2006 | 07 | 2006 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $756 | $359 | Not Implemented |
LL0260 # 08 Y:2006 | 08 | 2006 | INSTALL OCCUPANCY SENSORS | $751 | $600 | Not Implemented |
GT0826 # 01 Y:2006 | 01 | 2006 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $8,555 | $0 | Implemented |
GT0826 # 02 Y:2006 | 02 | 2006 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $3,095 | $13,342 | Not Implemented |
GT0826 # 03 Y:2006 | 03 | 2006 | INSTALL OCCUPANCY SENSORS | $454 | $280 | Not Implemented |
GT0826 # 04 Y:2006 | 04 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,167 | $23,331 | Not Implemented |
GT0826 # 05 Y:2006 | 05 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $746 | $400 | Not Implemented |
GT0826 # 06 Y:2006 | 06 | 2006 | COMBINE UTILITY METERS | $2,907 | $7,120 | Not Implemented |
GT0826 # 07 Y:2006 | 07 | 2006 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $282 | $234 | Not Implemented |
MI0131 # 01 Y:2006 | 01 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $42,001 | $40,224 | Implemented |
MI0131 # 02 Y:2006 | 02 | 2006 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $41,642 | $6,538 | Implemented |
MI0131 # 03 Y:2006 | 03 | 2006 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $16,391 | $29,320 | Implemented |
MI0131 # 04 Y:2006 | 04 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,321 | $1,074 | Implemented |