Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
12
matching recommendationsNAICS | 332510 | Hardware Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0492 # 01 Y:2014 | 01 | 2014 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $8,061 | $1,700 | Implemented |
WV0492 # 02 Y:2014 | 02 | 2014 | COVER OPEN TANKS | $7,268 | $1,145 | Implemented |
WV0492 # 03 Y:2014 | 03 | 2014 | TURN OFF EQUIPMENT WHEN NOT IN USE | $6,370 | $0 | Not Implemented |
WV0492 # 04 Y:2014 | 04 | 2014 | USE RADIANT HEATER FOR SPOT HEATING | $5,334 | $11,360 | Not Implemented |
WV0492 # 05 Y:2014 | 05 | 2014 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,126 | $3,000 | Implemented |
WV0492 # 06 Y:2014 | 06 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,774 | $8,160 | Implemented |
WV0492 # 07 Y:2014 | 07 | 2014 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $1,914 | $1,000 | Implemented |
WV0492 # 08 Y:2014 | 08 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,697 | $338 | Implemented |
WV0492 # 09 Y:2014 | 09 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $811 | $30 | Not Implemented |
WV0492 # 10 Y:2014 | 10 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $557 | $1,916 | Implemented |
WV0492 # 11 Y:2014 | 11 | 2014 | DEVELOP A REPAIR/REPLACE POLICY | $482 | $356 | Implemented |
WV0492 # 12 Y:2014 | 12 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $185 | $700 | Implemented |