Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
34
matching recommendationsNAICS | 33261 | Spring and Wire Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UC2310 # 05 Y:2023 | 05 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $6,045 | $40,103 | Implemented |
UC2310 # 06 Y:2023 | 06 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,547 | $1,283 | Implemented |
UC2310 # 07 Y:2023 | 07 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,607 | $1,900 | Implemented |
UC2310 # 10 Y:2023 | 10 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,459 | $150 | Implemented |
UC2310 # 01 Y:2023 | 01 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $4,838 | $0 | Implemented |
UC2310 # 08 Y:2023 | 08 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,756 | $225 | Implemented |
UC2310 # 12 Y:2023 | 12 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $791 | $1,804 | Not Implemented |
UC2310 # 02 Y:2023 | 02 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,116 | $0 | Implemented |
UC2310 # 09 Y:2023 | 09 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,865 | $5,326 | Implemented |
UC2310 # 03 Y:2023 | 03 | 2023 | PAY UTILITY BILLS ON TIME | $146 | $0 | Implemented |
UC2310 # 04 Y:2023 | 04 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $39,506 | $192,621 | Not Implemented |
UC2310 # 11 Y:2023 | 11 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,068 | $75 | Implemented |
UC2310 # 13 Y:2023 | 13 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $1,947 | $1,980 | Not Implemented |
MZ0346 # 05 Y:2023 | 05 | 2023 | INSTALL OCCUPANCY SENSORS | $146 | $200 | Implemented |
MZ0346 # 04 Y:2023 | 04 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $425 | $485 | Not Implemented |
MZ0346 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $825 | $2,925 | Implemented |
MZ0346 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $967 | $320 | Not Implemented |
MZ0346 # 03 Y:2023 | 03 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,048 | $6,536 | Not Implemented |
DL0221 # 14 Y:2023 | 14 | 2023 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $2,645 | $500 | Implemented |
DL0221 # 13 Y:2023 | 13 | 2023 | REPAIR AND ELIMINATE STEAM LEAKS | $53,076 | $20,000 | Implemented |
DL0221 # 12 Y:2023 | 12 | 2023 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $6,218 | $1,080 | Implemented |
DL0221 # 11 Y:2023 | 11 | 2023 | INSTALL / REPAIR INSULATION ON STEAM LINES | $812 | $2,301 | Implemented |
DL0221 # 08 Y:2023 | 08 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $75 | $200 | Not Implemented |
DL0221 # 06 Y:2023 | 06 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $293 | $0 | Implemented |
DL0221 # 05 Y:2023 | 05 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $740 | $1,500 | Not Implemented |