IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

97

matching recommendations
Reset
NAICS 333 Machinery Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UK1402 # 01 Y:2014 01 2014 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,710 $4,500 Not Implemented
UK1402 # 02 Y:2014 02 2014 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,696 $1,000 Not Implemented
UK1402 # 03 Y:2014 03 2014 MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT $2,530 $1,500 Not Implemented
UK1402 # 04 Y:2014 04 2014 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $1,833 $0 Not Implemented
UK1402 # 05 Y:2014 05 2014 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING $34,700 $40,000 Not Implemented
UK1402 # 06 Y:2014 06 2014 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE $1,409 $0 Not Implemented
UK1402 # 07 Y:2014 07 2014 USE PHOTOCELL CONTROLS $1,297 $1,125 Not Implemented
UK1402 # 08 Y:2014 08 2014 INSTALL OCCUPANCY SENSORS $11,101 $3,241 Not Implemented
UK1314 # 01 Y:2013 01 2013 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $12,434 $44,000 Implemented
UK1314 # 02 Y:2013 02 2013 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $7,512 $28,560 Implemented
UK1314 # 03 Y:2013 03 2013 RECOVER WASTE HEAT FROM EQUIPMENT $3,739 $4,500 Implemented
UK1314 # 04 Y:2013 04 2013 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $5,453 $15,000 Implemented
UK1314 # 05 Y:2013 05 2013 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $4,066 $0 Implemented
UK1314 # 10 Y:2013 10 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $690 $690 Implemented
UK1314 # 09 Y:2013 09 2013 USE PHOTOCELL CONTROLS $328 $592 Implemented
UK1314 # 08 Y:2013 08 2013 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $798 $700 Implemented
UK1314 # 07 Y:2013 07 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $1,662 $650 Implemented
UK1314 # 06 Y:2013 06 2013 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $2,594 $0 Implemented
UK1214 # 04 Y:2012 04 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $546 $500 Not Implemented
UK1214 # 03 Y:2012 03 2012 OPTIMIZE PLANT POWER FACTOR $6,631 $11,880 Not Implemented
UK1214 # 02 Y:2012 02 2012 UPGRADE CONTROLS ON COMPRESSORS $10,251 $11,250 Not Implemented
UK1214 # 01 Y:2012 01 2012 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER $57,123 $150,767 Not Implemented