Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,242
matching recommendationsNAICS | 3331 | Agriculture, Construction, and Mining Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1143 # 06 Y:2025 | 06 | 2025 | OPTIMIZE PLANT POWER FACTOR | $1,479 | $2,457 | n/a |
OK1143 # 01 Y:2025 | 01 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $693 | $3,315 | n/a |
OK1143 # 02 Y:2025 | 02 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $3,424 | $25,650 | n/a |
OK1143 # 05 Y:2025 | 05 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,910 | $4,426 | n/a |
OK1143 # 03 Y:2025 | 03 | 2025 | INSTALL TIMERS AND/OR THERMOSTATS | $1,973 | $1,950 | n/a |
OK1143 # 04 Y:2025 | 04 | 2025 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $609 | $4,675 | n/a |
WM0244 # 01 Y:2025 | 01 | 2025 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $22,838 | $0 | n/a |
WM0244 # 04 Y:2025 | 04 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,099 | $1,720 | n/a |
WM0244 # 03 Y:2025 | 03 | 2025 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,421 | $2,740 | n/a |
WM0244 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,400 | $4,125 | n/a |
AM0945 # 01 Y:2025 | 01 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $89,490 | $1,237,270 | n/a |
AM0945 # 05 Y:2025 | 05 | 2025 | OPTIMIZE PLANT POWER FACTOR | $30,475 | $47,407 | n/a |
AM0945 # 10 Y:2025 | 10 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,010 | $30 | n/a |
AM0945 # 08 Y:2025 | 08 | 2025 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $22,560 | $681,000 | n/a |
AM0945 # 06 Y:2025 | 06 | 2025 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $29,000 | $4,680 | n/a |
AM0945 # 03 Y:2025 | 03 | 2025 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $280,830 | $15,000 | n/a |
AM0945 # 04 Y:2025 | 04 | 2025 | USE BATTERY STORAGE FOR DEMAND CONTROL | $35,800 | $170,380 | n/a |
AM0945 # 09 Y:2025 | 09 | 2025 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $5,120 | $6,600 | n/a |
AM0945 # 07 Y:2025 | 07 | 2025 | USE COLD WASTE WATER TO COOL CHILLER FEED WATER | $26,500 | $2,650 | n/a |
AM0945 # 02 Y:2025 | 02 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $41,200 | $9,349 | n/a |
AM0945 # 11 Y:2025 | 11 | 2025 | USE SYNTHETIC LUBRICANT | $841 | $0 | n/a |
NL0108 # 02 Y:2025 | 02 | 2025 | UPGRADE OBSOLETE EQUIPMENT | $93,844 | $220,000 | n/a |
NL0108 # 04 Y:2025 | 04 | 2025 | INSTALL OCCUPANCY SENSORS | $686 | $1,621 | n/a |
NL0108 # 03 Y:2025 | 03 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,935 | $695 | n/a |
NL0108 # 01 Y:2025 | 01 | 2025 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $510,000 | $2,500,000 | n/a |