Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
198
matching recommendationsNAICS | 333241 | Food Product Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UC2507 # 03 Y:2024 | 03 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $16,863 | $129,193 | n/a |
UC2507 # 01 Y:2024 | 01 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $8,064 | $112,141 | n/a |
UC2507 # 06 Y:2024 | 06 | 2024 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $18,635 | $50 | n/a |
UC2507 # 04 Y:2024 | 04 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $2,335 | $6,240 | n/a |
UC2507 # 02 Y:2024 | 02 | 2024 | OPTIMIZE PLANT POWER FACTOR | $3,899 | $12,217 | n/a |
UC2507 # 05 Y:2024 | 05 | 2024 | INSULATE BARE EQUIPMENT | $1,482 | $2,236 | n/a |
MU0025 # 06 Y:2023 | 06 | 2023 | USE OPTIMUM TEMPERATURE | $1,361 | $0 | Implemented |
MU0025 # 05 Y:2023 | 05 | 2023 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $382 | $690 | Not Implemented |
MU0025 # 04 Y:2023 | 04 | 2023 | KEEP EQUIPMENT CLEAN | $332 | $0 | Implemented |
MU0025 # 03 Y:2023 | 03 | 2023 | INSTALL OCCUPANCY SENSORS | $37 | $50 | Implemented |
MU0025 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,096 | $0 | Implemented |
MU0025 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,630 | $360 | Implemented |
MU0025 # 09 Y:2023 | 09 | 2023 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $13,952 | $19,852 | Implemented |
MU0025 # 08 Y:2023 | 08 | 2023 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $431 | $0 | Implemented |
MU0025 # 07 Y:2023 | 07 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,434 | $2,876 | Implemented |
MU0025 # 10 Y:2023 | 10 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,348 | $9,576 | Not Implemented |
GT0942 # 01 Y:2020 | 01 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $20,227 | $1,450 | Implemented |
GT0942 # 02 Y:2020 | 02 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,618 | $2,500 | Implemented |
GT0942 # 05 Y:2020 | 05 | 2020 | MINIMIZE WATER USAGE | $3,202 | $5,700 | Not Implemented |
GT0942 # 07 Y:2020 | 07 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $114,607 | $699,103 | Not Implemented |
GT0942 # 03 Y:2020 | 03 | 2020 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $14,945 | $4,781 | Not Implemented |
GT0942 # 06 Y:2020 | 06 | 2020 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $113,048 | $690,000 | Not Implemented |
GT0942 # 04 Y:2020 | 04 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $50,179 | $71,763 | Not Implemented |
LS1909 # 05 Y:2019 | 05 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $447 | $300 | Not Implemented |
LS1909 # 06 Y:2019 | 06 | 2019 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $651 | $635 | Not Implemented |