Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
466
matching recommendationsNAICS | 3333 | Commercial and Service Industry Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0841 # 16 Y:2011 | 16 | 2011 | INSTALL AUTOMATIC STACK DAMPER | $20,178 | $500 | Not Implemented |
UD0841 # 17 Y:2011 | 17 | 2011 | INSTALL AUTOMATIC STACK DAMPER | $20,941 | $600 | Implemented |
UD0841 # 18 Y:2011 | 18 | 2011 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,133 | $2,098 | Implemented |
UD0841 # 19 Y:2011 | 19 | 2011 | REDUCE VENTILATION AIR | $174,913 | $242,291 | Not Implemented |
UD0841 # 20 Y:2011 | 20 | 2011 | USE RADIANT HEATER FOR SPOT HEATING | $4,098 | $17,940 | Not Implemented |
UD0841 # 21 Y:2011 | 21 | 2011 | USE RADIANT HEATER FOR SPOT HEATING | $2,147 | $4,000 | Not Implemented |
LL0355 # 01 Y:2011 | 01 | 2011 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $121,680 | $22,440 | Implemented |
LL0355 # 02 Y:2011 | 02 | 2011 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $7,278 | $4,106 | Implemented |
LL0355 # 03 Y:2011 | 03 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,642 | $1,680 | Implemented |
LL0355 # 04 Y:2011 | 04 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,751 | $11,200 | Implemented |
LL0355 # 05 Y:2011 | 05 | 2011 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,231 | $270 | Not Implemented |
LL0355 # 06 Y:2011 | 06 | 2011 | INSTALL OCCUPANCY SENSORS | $2,199 | $2,220 | Not Implemented |
LL0355 # 07 Y:2011 | 07 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $746 | $1,155 | Not Implemented |
LL0355 # 08 Y:2011 | 08 | 2011 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $238 | $368 | Not Implemented |
LL0355 # 09 Y:2011 | 09 | 2011 | INSULATE BARE EQUIPMENT | $7 | $18 | Not Implemented |
CO0641 # 01 Y:2010 | 01 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,720 | $410 | Not Implemented |
CO0641 # 02 Y:2010 | 02 | 2010 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,220 | $3,400 | Not Implemented |
CO0641 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,910 | $5,160 | Not Implemented |
CO0641 # 04 Y:2010 | 04 | 2010 | USE SOLAR HEAT TO MAKE ELECTRICTY | $4,170 | $31,500 | Not Implemented |
CO0641 # 05 Y:2010 | 05 | 2010 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $3,610 | $2,880 | Not Implemented |
CO0641 # 06 Y:2010 | 06 | 2010 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,270 | $35,500 | Not Implemented |
CO0641 # 07 Y:2010 | 07 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,300 | $5,160 | Not Implemented |
CO0641 # 08 Y:2010 | 08 | 2010 | INSTALL OCCUPANCY SENSORS | $520 | $810 | Not Implemented |
CO0641 # 09 Y:2010 | 09 | 2010 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $320 | $650 | Not Implemented |
MA0661 # 01 Y:2010 | 01 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $562 | $588 | Implemented |