IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,278

matching recommendations
Reset
NAICS 334 Computer and Electronic Product Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK1117 # 01 Y:2024 01 2024 INSTALL OCCUPANCY SENSORS $196 $563 Implemented
UU0251 # 02 Y:2024 02 2024 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE $27,500 $13,788 Implemented
UU0251 # 01 Y:2024 01 2024 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $38,394 $100,000 Implemented
UU0251 # 05 Y:2024 05 2024 DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS $8,918 $750 Implemented
UU0251 # 06 Y:2024 06 2024 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,210 $6,486 Implemented
IP0194 # 01 Y:2024 01 2024 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,623 $0 Implemented
IP0194 # 02 Y:2024 02 2024 USE OPTIMUM TEMPERATURE $2,876 $0 Implemented
IP0194 # 03 Y:2024 03 2024 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $1,317 $0 Implemented
IP0194 # 04 Y:2024 04 2024 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $1,154 $0 Implemented
IP0194 # 08 Y:2024 08 2024 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,174 $16,475 Implemented
OK1113 # 01 Y:2024 01 2024 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $3,139 $4,760 Implemented
OK1113 # 05 Y:2024 05 2024 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $125 $611 Implemented
OK1113 # 02 Y:2024 02 2024 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,798 $1,675 Implemented
SD0656 # 10 Y:2024 10 2024 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,299 $3,896 Implemented
SD0656 # 09 Y:2024 09 2024 PREVENT EXCESSIVE SOLVENT USAGE (OPERATOR TRAINING) $35,678 $51,900 Implemented
SD0656 # 08 Y:2024 08 2024 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,188 $500 Implemented
SD0656 # 07 Y:2024 07 2024 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,422 $2,040 Implemented
AS0572 # 07 Y:2024 07 2024 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $258 $79 Implemented
AS0572 # 05 Y:2024 05 2024 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,321 $1,387 Implemented
AS0572 # 04 Y:2024 04 2024 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE $1,801 $1,399 Implemented
AS0572 # 03 Y:2024 03 2024 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,426 $278 Implemented
AS0572 # 01 Y:2024 01 2024 INSTALL BACK-UP EQUIPMENT $53,208 $12,653 Implemented
AS0569 # 01 Y:2023 01 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $30,436 $18,656 Implemented
AS0569 # 03 Y:2023 03 2023 INSTALL OCCUPANCY SENSORS $5,717 $3,715 Implemented
AS0569 # 06 Y:2023 06 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $327 $146 Implemented