Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
13
matching recommendationsNAICS | 334220 | Radio and Television Broadcasting and Wireless Communications Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0263 # 01 Y:2004 | 01 | 2004 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $69,923 | $48,000 | Not Implemented |
MS0263 # 02 Y:2004 | 02 | 2004 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $23,031 | $6,075 | Not Implemented |
MS0263 # 03 Y:2004 | 03 | 2004 | USE RADIANT HEATER FOR SPOT HEATING | $22,043 | $11,115 | Not Implemented |
MS0263 # 04 Y:2004 | 04 | 2004 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $9,604 | $14,973 | Not Implemented |
MS0263 # 05 Y:2004 | 05 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,761 | $15,789 | Not Implemented |
MS0263 # 06 Y:2004 | 06 | 2004 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $7,294 | $50 | Not Implemented |
MS0263 # 07 Y:2004 | 07 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,750 | $69 | Not Implemented |
MS0263 # 08 Y:2004 | 08 | 2004 | PAY UTILITY BILLS ON TIME | $968 | $100 | Not Implemented |
SU0178 # 01 Y:2004 | 01 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $26,400 | $0 | Implemented |
SU0178 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,746 | $527 | Implemented |
SU0178 # 03 Y:2004 | 03 | 2004 | INSTALL OCCUPANCY SENSORS | $580 | $214 | Implemented |
SU0178 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,209 | $20,138 | Not Implemented |
SU0178 # 05 Y:2004 | 05 | 2004 | OPTIMIZE PLANT POWER FACTOR | $5,392 | $15,432 | Implemented |