Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
10
matching recommendationsNAICS | 335931 | Current-Carrying Wiring Device Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0824 # 01 Y:2020 | 01 | 2020 | REPLACE BOILER | $15,999 | $29,000 | Not Implemented |
MA0824 # 02 Y:2020 | 02 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $10,379 | $54,695 | Not Implemented |
MA0824 # 03 Y:2020 | 03 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,177 | $29,750 | Implemented |
MA0824 # 04 Y:2020 | 04 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,118 | $7,710 | Implemented |
MA0824 # 05 Y:2020 | 05 | 2020 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $1,491 | $6,300 | Implemented |
OK1029 # 01 Y:2020 | 01 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,568 | $2,250 | Implemented |
OK1029 # 02 Y:2020 | 02 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,512 | $0 | Not Implemented |
OK1029 # 03 Y:2020 | 03 | 2020 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $4,684 | $22,100 | Implemented |
OK1029 # 04 Y:2020 | 04 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,197 | $30,672 | Implemented |
OK1029 # 05 Y:2020 | 05 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $546 | $522 | Not Implemented |