Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
34
matching recommendationsNAICS | 336413 | Other Aircraft Parts and Auxiliary Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0721 # 09 Y:2013 | 09 | 2013 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,465 | $1,650 | Not Implemented |
MA0721 # 01 Y:2013 | 01 | 2013 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $15,477 | $1,400 | Not Implemented |
MA0721 # 02 Y:2013 | 02 | 2013 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $10,906 | $7,500 | Implemented |
MA0721 # 03 Y:2013 | 03 | 2013 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $7,493 | $11,000 | Implemented |
MA0721 # 04 Y:2013 | 04 | 2013 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $4,864 | $200 | Implemented |
MA0721 # 05 Y:2013 | 05 | 2013 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,474 | $200 | Implemented |
MA0721 # 06 Y:2013 | 06 | 2013 | REPAIR AND ELIMINATE STEAM LEAKS | $2,358 | $1,120 | Implemented |
MA0721 # 07 Y:2013 | 07 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,130 | $1,020 | Implemented |
MA0721 # 08 Y:2013 | 08 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,106 | $6,390 | Not Implemented |
MA0713 # 05 Y:2013 | 05 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,837 | $1,720 | Implemented |
MA0713 # 04 Y:2013 | 04 | 2013 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,564 | $16,800 | Not Implemented |
MA0713 # 03 Y:2013 | 03 | 2013 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $7,547 | $44,500 | Not Implemented |
MA0713 # 02 Y:2013 | 02 | 2013 | REDUCE VENTILATION AIR | $7,745 | $500 | Implemented |
MA0713 # 01 Y:2013 | 01 | 2013 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $7,896 | $22,000 | Not Implemented |
MA0695 # 10 Y:2012 | 10 | 2012 | INSULATE BARE EQUIPMENT | $2,281 | $2,630 | Not Implemented |
MA0695 # 12 Y:2012 | 12 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $768 | $510 | Not Implemented |
MA0695 # 11 Y:2012 | 11 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,309 | $1,260 | Implemented |
MA0695 # 09 Y:2012 | 09 | 2012 | INSTALL OCCUPANCY SENSORS | $2,470 | $7,725 | Not Implemented |
MA0695 # 01 Y:2012 | 01 | 2012 | BURN A LESS EXPENSIVE GRADE OF FUEL | $24,095 | $20,000 | Not Implemented |
MA0695 # 02 Y:2012 | 02 | 2012 | TURN OFF EQUIPMENT WHEN NOT IN USE | $22,626 | $5,600 | Implemented |
MA0695 # 03 Y:2012 | 03 | 2012 | TURN OFF EQUIPMENT WHEN NOT IN USE | $8,891 | $200 | Implemented |
MA0695 # 04 Y:2012 | 04 | 2012 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $6,220 | $11,500 | Implemented |
MA0695 # 05 Y:2012 | 05 | 2012 | OPTIMIZE PLANT POWER FACTOR | $5,965 | $10,975 | Implemented |
MA0695 # 06 Y:2012 | 06 | 2012 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,830 | $1,000 | Not Implemented |
MA0695 # 07 Y:2012 | 07 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,676 | $1,000 | Implemented |