IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

17

matching recommendations
Reset
NAICS 3371 Household and Institutional Furniture and Kitchen Cabinet Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK1086 # 04 Y:2023 04 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $31,948 $382,200 Not Implemented
OK1086 # 03 Y:2023 03 2023 USE RADIANT HEATER FOR SPOT HEATING $8,472 $13,560 Not Implemented
OK1086 # 02 Y:2023 02 2023 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $630 $330 Implemented
OK1086 # 01 Y:2023 01 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,012 $1,489 Implemented
OK0774 # 02 Y:2009 02 2009 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,831 $0 Implemented
OK0774 # 06 Y:2009 06 2009 $400 $0 Not Implemented
OK0774 # 05 Y:2009 05 2009 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $825 $5,760 Not Implemented
OK0774 # 04 Y:2009 04 2009 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $229 $1,891 Not Implemented
OK0774 # 03 Y:2009 03 2009 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $365 $1,154 Implemented
OK0774 # 01 Y:2009 01 2009 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $607 $1,902 Not Implemented
OK0747 # 01 Y:2007 01 2007 RECOVER WASTE HEAT FROM EQUIPMENT $7,165 $4,559 Implemented
OK0747 # 07 Y:2007 07 2007 $2,068 $200 Not Implemented
OK0747 # 06 Y:2007 06 2007 INSTALL SKYLIGHTS $22,903 $139,000 Not Implemented
OK0747 # 05 Y:2007 05 2007 USE SOLAR HEAT FOR HEAT $14,978 $138,320 Not Implemented
OK0747 # 04 Y:2007 04 2007 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $7,099 $0 Not Implemented
OK0747 # 03 Y:2007 03 2007 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,756 $0 Not Implemented
OK0747 # 02 Y:2007 02 2007 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $991 $326 Not Implemented