Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
40
matching recommendationsNAICS | 33911 | Medical Equipment and Supplies Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0118 # 02 Y:2017 | 02 | 2017 | USE OPTIMUM TEMPERATURE | $7,381 | $0 | Implemented |
UU0118 # 01 Y:2017 | 01 | 2017 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $13,592 | $500 | Not Implemented |
SD0549 # 04 Y:2017 | 04 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $638 | $600 | Implemented |
SD0549 # 01 Y:2017 | 01 | 2017 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $49,288 | $204,000 | Implemented |
SD0549 # 02 Y:2017 | 02 | 2017 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $16,056 | $3,882 | Implemented |
SD0549 # 05 Y:2017 | 05 | 2017 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $360 | $300 | Implemented |
SD0549 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,048 | $4,352 | Implemented |
UU0116 # 07 Y:2017 | 07 | 2017 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $4,500 | $200 | Not Implemented |
UU0116 # 08 Y:2017 | 08 | 2017 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $59,018 | $500 | Implemented |
UU0116 # 06 Y:2017 | 06 | 2017 | INSTALL SPECTRAL REFLECTORS / DELAMP | $901 | $142 | Implemented |
UU0116 # 05 Y:2017 | 05 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,534 | $2,402 | Implemented |
UU0116 # 04 Y:2017 | 04 | 2017 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,620 | $580 | Not Implemented |
UU0116 # 03 Y:2017 | 03 | 2017 | REDUCE VENTILATION AIR | $61,065 | $0 | Not Implemented |
UU0116 # 02 Y:2017 | 02 | 2017 | USE OPTIMUM TEMPERATURE | $6,759 | $0 | Not Implemented |
UU0116 # 01 Y:2017 | 01 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,863 | $0 | Implemented |