Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
12
matching recommendationsNAICS | 339113 | Surgical Appliance and Supplies Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0562 # 01 Y:2018 | 01 | 2018 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $27,423 | $97,740 | Implemented |
SD0562 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,835 | $13,230 | Implemented |
SD0562 # 04 Y:2018 | 04 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,214 | $1,000 | Implemented |
SD0562 # 05 Y:2018 | 05 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,279 | $600 | Implemented |
SD0560 # 02 Y:2018 | 02 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $14,240 | $11,880 | Implemented |
SD0560 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,961 | $19,600 | Implemented |
SD0560 # 04 Y:2018 | 04 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,948 | $1,200 | Implemented |
SF0466 # 02 Y:2015 | 02 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,015 | $5,614 | Implemented |
SF0466 # 03 Y:2015 | 03 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,885 | $5,614 | Implemented |
SF0466 # 04 Y:2015 | 04 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,752 | $2,224 | Implemented |
SF0466 # 05 Y:2015 | 05 | 2015 | INSTALL OCCUPANCY SENSORS | $5,556 | $6,409 | Implemented |
SF0466 # 06 Y:2015 | 06 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,026 | $4,733 | Implemented |