Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
33
matching recommendationsNAICS | 511 | Publishing Industries (except Internet) |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0294 # 01 Y:2005 | 01 | 2005 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $7,821 | $400 | Implemented |
BD0294 # 02 Y:2005 | 02 | 2005 | INSTALL OCCUPANCY SENSORS | $1,291 | $750 | Not Implemented |
BD0294 # 05 Y:2005 | 05 | 2005 | EXPAND OPERATIONS INTO UNUSED SPACE | $40,952 | $20,000 | Implemented |
BD0294 # 07 Y:2005 | 07 | 2005 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $8,840 | $3,000 | Implemented |
BD0294 # 06 Y:2005 | 06 | 2005 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $13,260 | $2,000 | Implemented |
BD0294 # 03 Y:2005 | 03 | 2005 | INSULATE BARE EQUIPMENT | $599 | $263 | Implemented |
BD0294 # 04 Y:2005 | 04 | 2005 | INSTALL AUTOMATIC PACKING EQUIPMENT | $41,600 | $22,000 | Implemented |
SF0307 # 04 Y:2005 | 04 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $268 | $653 | Implemented |
SF0307 # 03 Y:2005 | 03 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,884 | $4,039 | Not Implemented |
SF0307 # 02 Y:2005 | 02 | 2005 | INSTALL OCCUPANCY SENSORS | $1,962 | $3,472 | Not Implemented |
SF0307 # 01 Y:2005 | 01 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $8,571 | $0 | Implemented |
MI0105 # 05 Y:2005 | 05 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $7,381 | $14,100 | Not Implemented |
MI0105 # 06 Y:2005 | 06 | 2005 | DISCONNECT BALLASTS | $4,619 | $0 | Not Implemented |
MI0105 # 04 Y:2005 | 04 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $16,112 | $0 | Not Implemented |
MI0105 # 03 Y:2005 | 03 | 2005 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $26,325 | $32,000 | Not Implemented |
MI0105 # 02 Y:2005 | 02 | 2005 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $44,261 | $320 | Not Implemented |
MI0105 # 01 Y:2005 | 01 | 2005 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $81,540 | $120,000 | Not Implemented |
GT0807 # 01 Y:2005 | 01 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,729 | $25,590 | Implemented |
GT0807 # 09 Y:2005 | 09 | 2005 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $5,762 | $50,525 | Not Implemented |
GT0807 # 08 Y:2005 | 08 | 2005 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $497 | $1,300 | Implemented |
GT0807 # 07 Y:2005 | 07 | 2005 | METER WASTE WATER | $7,200 | $550 | Not Implemented |
GT0807 # 06 Y:2005 | 06 | 2005 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,540 | $1,120 | Not Implemented |
GT0807 # 05 Y:2005 | 05 | 2005 | COMBINE UTILITY METERS | $3,880 | $8,000 | Not Implemented |
GT0807 # 04 Y:2005 | 04 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $427 | $120 | Implemented |
GT0807 # 03 Y:2005 | 03 | 2005 | INSTALL OCCUPANCY SENSORS | $1,135 | $543 | Implemented |